Plan Review Details - Permit 06060692
Plan Review Stops For Permit 06060692
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2006-07-27 Cont ID  
Sent By alange Date 2006-07-27 Time 15:34 Rev Time 0.00
Received By alange Date 2006-07-27 Time 15:34 Sent To  
Notes
2006-07-27 00:00:00DENIED
  
  
 1.BEFORE A PERMIT TO CONSTRUCT, MAY BE
 ISSUED, IMPACT FEES MUST BE PAID TO PALM
 BEACH COUNTY. THE ACTUAL PERMIT SET OF
 PLANS MUST BE STAMPED BY THAT OFFICE,
 AND A COPY OF THE PAID RECEIPT ATTACHED
 TO THE PERMIT APPLICATION. PLEASE CALL
 (561)233-5025 FOR MORE INFORMATION.
  
 2.PERMIT VALUE SHOULD REFLECT THE
 COSTS OF ALL MATERIALS AND LABOR.
 ADJUST PERMIT VALUE OR WE WILL ADJUST IT
 ACCORDING TO MARSHALL AND SWIFT
 ESTIMATING GUIDE. ADDITIONAL PERMIT FEES
 ARE DUE.
  
 3.SUBMIT TWO COPIES OF ENERGY CALCS
 PER 2004 FBC.
  
 4.PRODUCT APPROVALS REQUIRED FOR
 STANDING SEAM ROOF, BASE UNDERLAYMENT
 FOR METAL ROOF, FLAT ROOF, STRAPS AND
 TIE-DOWNS AND EXTEWRIOR HOLLOW METAL
 DOOR.
  
 5.ALL PRODUCT APPROVALS SUBMITTED WITH
 QUALITY ASSURANCE SHALL HAVE THE
 FOLLOWING STATE APPROVAL ATTACHED.
  
 PRODUCT APPROVALS SUBMITTED WITH
 PERMIT APPLICATION AFTER OCTOBER 1, 2003
 ARE REQUIRED TO COMPLY WITH THE FLORIDA
 PRODUCT APPROVAL SYSTEM. FOR INFORMATION
 PLEASE SEE THE STATE WEBSITE AT
 WWW.FLORIDABUILDING.ORG. PRODUCTS WITH
 STATEWIDE APPROVAL ARE REQUIRED TO BE
 SUBMITTED WITH A STATE PRODUCT APPROVAL
 SHEETS THAT LISTS THE PRODUCT IDENTITY
 NUMBER FROM THE STATE. IF THE PRODUCT
 DOES NOT HAVE STATEWIDE APPROVAL, SUBMIT
 AN APPLICATION FOR LOCAL PRODUCT
 APPROVAL OR SITE SPECIFIC FORM PER RULE
 9B-72. SEE ATTACHMENT.
 WWW.FLORIDABUILDING.ORG
  
 6.THOSE PRODUCT APPROVALS WHICH ARE
 REGULATED BY DCA RULE 9B-72 SHALL BE
 REVIEWED AND APPROVED IN WRITING BY THE
 DESIGNER OF RECORD PRIOR TO SUBMITTAL
 FOR JURISDICTIONAL APPROVAL.WPB
 AMENDMENT TO FBC 106.3.3.
  
 7.SUBMIT TWO SETS OF TRUSS DRAWINGS
 FOR REVIEW PER 2004 FBC R-802.10.1
 TRUSS DRAWING REQUIRED TO BE APPROVED
 PRIOR TO INSTALLATION.
  
 8.A DESIGN PROFESSIONAL OR AN OWNER
 MUST ELECT ONE OR A COMBINATION OF
 LEVELS OF ALTERATION PURSUANT TO
 SECTIONS 303, 304 AND 305 OF THIS CODE.
 SHOW HOW PLANS WILL COMPLY WITH THE
 SECTION(S) SELECTED.2004 FBC EXISTING
 BUILDING 301.5
  
 9.DOOR CLEARANCES, BATHROOM DOOR TO
 LADIES RESTROOM AND MANAGERS OFFICE
 SHALL HAVE A MINIMUM 18" CLEARANCE AT
 THE LATCH SIDE OF THE DOOR. SEE DIAGRAMS
 AT FBC 11.66.
  
 10.MINIMUM PLAN REVIEW CRITERIA FOR
 BUILDINGS FBC 106.3.5 SHOW THE FOLLOWING
 INFORMATION ON PLANS.
 A. CONSTRUCTION TYPE
 B. OCCUPANCY GROUP
 C. OCCUPANT LOAD
 D. SPRINKLERED OR NOT
 E. CURRENT CODE SECTIONS USED
  
 11.INCLUDE A LIFE SAFTEY PLAN AND
 INCLUDE EXIT ACCESS TRAVEL DISTANCE. FBC
 1015.1
  
 12.SUBMIT TWO ORIGONAL SIGNED AND
 SEALED SURVEYS, FS. 472.025
  
 13.SHOW ACCESSABLE ROUTE FROM PARKING
 AREA INTO THE BUILDING FBC 11.4.3
  
 14.SHOW ROOF AND WALL SHEATHING
 COMPLYING WITH TABLE 2304.9.1 #31 FOR
 THICKNESS AND FASTENING SCHEDULE.
  
 15.A SEPERATE PERMIT IT REQUIRED FOR
 AWNINGS.
  
 16.SHOW SERVICE COUNTERS COMPLYING
 WITH FBC 11-7.2
  
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE
 THE REVISION & REMOVE & REPLACE ANY
 PAGES AS NECESSARY. SUBMIT ONE COPY OF
 OLD PAGES FOR REFERENCE . A TRANSMITTAL
 LETTER LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER, WITH A DESCRIPTION OF
 THE REVISION MADE, IDENTIFYING THE SHEET
 OR SPECIFICATION PAGE WHERE THE CHANGES
 CAN BE FOUND WILL HELP TO EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 ART LANGE
 CONSTRUCTION SERVICES DEPARTMENT
 BUILDING PLANS EXAMINER
 561-805-6672
  
  
  

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2006-07-02 Cont ID  
Sent By dpalmer Date 2006-07-02 Time 08:37 Rev Time 0.00
Received By dpalmer Date 2006-07-02 Time 08:01 Sent To  
Notes
2006-07-02 00:00:00IN ELEC FOR REVIEW
 **** UNSAT*****
  
 1) NOTE: PLEASE SEE THE FOLLOWING CODES
 SHALL BE REFERENCED ON ELECTRICAL PLANS.
 2002 NFPA-70 (NEC), 2002 NFPA-72, 2003
 NFPA-101
  
 2) NOTE: PLEASE SUBMIT A MINIMUM OF TWO
 SETS OF PLANS, UP TO THREE SETS WILL BE
 STAMPED , FOUR SETS WERE SUBMITTED.
 PLEASE SEE NO "POWER" PLANS WAS
 SUBMITTED IN SETS FOR REVIEW?
 215.5,FBC 106.1.2 ADMIN SECT.
  
 3) NOTE: PLEASE SEE 210.8B3 FOR
 REQUIREMENTS OF AREAS IN KITCHEN AND
 AREA OF THE LIKE. PLEASE SEE THIS
 REQUIRES GFI PROTECTION.
  
 4) NOTE: PLEASE SEE THERE APPEARS TO BE
 AN "EQUIPMENT GROUNDING CONDUCTOR" FROM
 METER "CT" TO MAIN "DP". PLEASE SEE
 250.6,250.24B, EQUIPMENT GRNDS ARE ONLY
 INSTALLED AFTER THE FIRST MEANS OF
 DISCONNECT.
 "OBJECTIONAL CURRENTS AND PARALLELING
 THE NEUTRAL"
  
 5) NOTE: PLEASE SHOW THE LOAD
 CALCULATIONS,
 220.3,220.10,220.11,220.13, ETC.
 PLEASE SHOW ALL CONTINUOUS LOADS AT
 125%,215.3,230.42
  
 6) NOTE: PLEASE SEE VALUE ON PERMIT
 APPLICATION IS LOW FOR TOTAL SCOPE OF
 WORK AS SHOWN ON PLANS. PLEASE SEE FBC
 ADMIN SECT 108.3 WHICH REQUIRES VALUE
 FOR SCOPE PF WORK TO INCLUDE ALL LABOR
 AND MATERIALS EVEN IF ANY MATERIALS ARE
 OWNER SUPPLIED. VALUE MAY BE ADJUSTED BY
 THIS OFFICE USING "MARSHALLS & SWIFT"
 GUIDE AS ADOPTED BY THE FBC SEC ABOVE.
  
 ** PLEASE BE SURE TO COMPLETELY REMOVE
 ANY OLD/VOIDED SHEETS FROM SETS AND ONLY
 INSERT NEW REVISED SHEETS INTO COMPLETE
 SETS FOR REVIEW AND STAMPING.
  
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE DO NOT HESITATE IN CONTACTING
 THIS OFFICE.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 561-805-6717
 [email protected]

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2006-08-18 Cont ID  
Sent By pkrauss Date 2006-08-18 Time 09:05 Rev Time 0.00
Received By pkrauss Date 2006-07-11 Time 09:33 Sent To  
Notes
2006-07-11 00:00:001. DEMOLITION, RENOVATION, AND
 CONSTRUCTION TO COMPLY WITH NFPA 241.
  
 2. DEBRIS SHALL BE REMOVED DAILY FROM
 THE SITE.
  
 3. EXITS SHALL BE PROVIDED DURING
 DEMOLITION.
  
 4. SUITABLE EMERGENCY LIGHTS AND EXIT
 SIGNS SHALL BE PROVIDED TO PROPERLY
 ILLUMINATE AND IDENTIFY THE MEANS OF
 EGRESS COMPONENTS.
  
 5. GAS COOKING EQUIPMENT SHALL COMPLY
 WITH ALL APPLICABLE FIRE CODE
 REQUIREMENTS.
  
 6. SEPARATE PLANS AND PERMITS REQUIRED
 FOR THE TYPE 1 HOOD IDENTIFIED ON PAGE
 M1.1.
  
 7. SEPARATE PLANS AND PERMITS REQUIRED
 FOR THE SUPPRESSION SYSTEM PLANNED FOR
 THE TYPE 1 HOOD.
  
 8. PLEASE INDICATE INTERIOR FINISH
 CLASSIFICATIONS FOR WALLS AND CEILINGS.
  
 9. BUILDING ADDRESS IS REQUIRED. A
 MINIMUM OF AT LEAST 6" HIGH NUMBERS ARE
 REQUIRED.
  
 10. IT WAS NOTED THAT THE ROOF MATERIALS
 WILL MEET CLASS A MATERIALS.
  
 11. EXIT SIGN APPEARS TO BE MISSING FROM
 SECOND EXIT DOOR.
  
  
 MIKE CARSILLO, CHIEF FIRE PREVENTION
 OFFICER
 804-4709

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2006-07-29 Cont ID  
Sent By pschmitz Date 2006-07-29 Time 11:48 Rev Time 0.00
Received By pschmitz Date 2006-07-29 Time 11:43 Sent To  
Notes
2006-07-29 00:00:00PAUL SCHMITZ
 [email protected]
 FBC 2004 FUEL GAS CODEPLAN REVIEW
  
 UNSAT
  
 A) THE FOLLOWING INFORMATION IS REQUIRED
 FOR THE GAS PERMIT:
  
 1. SUBMIT AN ISOMETRIC DRAWING THAT
 CLEARLY SHOWS TOTAL DEVELOPED LEGENTH.
  
 2. 3. TYPE OF GAS, (LP OR NATURAL)
  
 3. BTU LOAD OF EACH APPLIANCE AND THE
 TOTAL BTU LOAD ON THE SYSTEM. REFER TO
 THE FBC-2004 FUEL GAS CODE SECS. 401.8
 THRU 402.6.1 AND TABLES 402.4(1) THRU
 402.4(33).
  
 5. SHOW THE DISTANCE FROM THE POINT OF
 DELIVERY, (METER), TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND/OR SYSTEM PER
 FBC-2004 FUEL GAS CODE APPENDIX A - USE
 OF CAPACITY TABLES A.3.1(4).
  
 6. SUBMIT CALCULATIONS FOR COMBUSTION
 AIR (IF APPLICABLE) PER FBC-2004 FUEL
 GAS CODE SECTION 304
 .
 7. INDICATE THE DELIVERY PRESSURE (PSI)
 PER FBC-2004 FUEL GAS CODE SEC. 402.2.
 NATURAL GAS SPECIFY .5 PSI OR 2 PSI.
 8. SUBMIT MANUFACTURE SHEETS FOR ALL GAS
 EQUIPMENT TO VERIFY COMPLIANCE WITH
 STANDARDS NFPA 54, NFPA 58, AND THE
 FBC-2001 FUEL GAS CODE SEC 402.2.
  
 9. SUBMIT MANUFACTURE SHEETS FOR ALL GAS
 EQUIPMENT TO VERIFY COMPLIANCE WITH
 STANDARDS NFPA 54, NFPA 58, AND THE
 FBC-2004 FUEL GAS CODE SEC 402.2.
  
 10. CLEARLY SHOW THE LOCATION AND CAP-
 ACITY OF LP TANK(S), TYPE OF TANK (DOT
 OR ASME), THE DISTANCE OF THE TANK FROM
 THE BUILDING AND ADJACENT PROPERTY LINES
 THE DISTANCE OF THE TANK FROM ALL SOUR-
 CES OF IGNITION, OTHER CONTAINERS, BUILD
 INGS, AND THE LOCATION OF ANY BUILDING
 OPENINGS BELOW THE RELIEF VALVE OF THE
 TANK PER NFPA 58, TABLE 3-2.2.2.
  
 11. CLEARLY INDICATE ON THE PLAN IF THE
 LP TANK IS ABOVE OR BELOW GROUND, AND
 SHOW REQUIRED PROTECTION OF THE TANK AND
 APPURTENANCES PER NFPA 58. IF THE TANK
 IS BELOW GROUND THE CONTAINER SHALL BE
 SECURILY ANCHORED PER NFPA 58 SECTION
 3-2.2.7(H).
  
 12. SEC 409.5 EQUIPMENT SHUT OFF VALVE.
 EMERGENCY HOOD SHUT DOWN SHUT OFF
 VALVE TO BE BELOW CEILING. MANUAL SHUT
 OFF VALVE TO BE UPSTREAM. UNION TO BE
 DOWNSTREAM OF MANUAL SHUT OFF VALVE.
  
 B)SHT P1.1 RFERENCE TO PROPANE GAS METER
 SHT P3.1 GAS ISOMETRIC NATURAL GAS.
 NEW GAS REGULATOR AND METER BY TECO GAS.
 GAS SPECIFICATIONS NOTE (B) REFERENCE TO
 TECO PEOPLES GAS CO.
 THE LOCAL NATURAL GAS IS SUPPLIED BY
 FLORIDA PUBLIC UTILITIES.
  
 C) SHT A1.4 EQUIPMENT SCHEDULE AE# 651
 SHOW THE LOCATION OF PASTA COOK STATION,
 INCLUDE THIS ON THE GASISOMETRIC
 DRAWING.
  
 QUESTIONS 561-805-6692PAUL SCHMITZ

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2006-08-18 Cont ID  
Sent By pkrauss Date 2006-08-18 Time 09:06 Rev Time 0.00
Received By pkrauss Date 2006-06-15 Time 09:32 Sent To  
Notes
2006-06-24 00:00:00TO COMM BOARD # 54, ALL TRADES. B, F,
 E, M , P
2006-06-15 00:00:00WAITING FOR "COMM" BD

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2006-08-17 Cont ID  
Sent By pkrauss Date 2006-08-17 Time 09:59 Rev Time 0.00
Received By pkrauss Date 2006-08-17 Time 09:59 Sent To  
Notes
2006-08-17 00:00:00DENIED:
 1.PLAN SHEET M0.1 VENTILATION
 COMPLIANCE STATEMENT, NOTE 1 INDICATES
 ASHRAE STANDARD 62-2004.THE ASHRAE
 STANDARD REFERENCED IN THE CURRENT CODE
 IS 62-2001.PLEASE CORRECT.
  
 2.PLAN SHEET M2.1 DETAIL 4 OF THE ROOF
 MOUNTED CURB.PER 2004 FBC 1509.7 ROOF
 MOUNTED MECHANICAL UNITS SHALL BE
 MOUNTED ON CURBS RAISED A MINIMUM OF 8"
 ABOVE THE ROOF SURFACE.
  
 3.ADDITIONAL PERMITS REQUIRED FOR
 HOODS, FIRE SUPPRESSION, AND WALK IN
 COOLERS.PLEASE PROVIDE PLANS AND
 MANUFACTURER'S SUBMITTAL DATA WITH
 PERMIT APPLICATION.
  
 PLANS FOR THE HOOD SHOULD INDICATE THE
 FOLLOWING:
 - INDICATE GAUGE OF THE GREASE DUCT AS
 WELL AS THE DUCT TO THE HEAT HOOD PER
 NFPA 96-01 CHAPTER 7 & 2004 FMC
 506.3.1.2.
  
 - ROOFTOP TERMINATION OF THE GREASE
 DUCT, SHOW COMPLIANCE WITH NFPA 96-2001
 SUB-CHAPTER 7.8.2.1, ITEMS 1 THROUGH 8.
  
 - PROVIDE AIR VELOCITY THROUGH DUCT PER
 2004 FMC 506.3.4.
  
 - PROVIDE A DETAIL FOR HANGING THE HOOD.
  
 - PROVIDE PLANS FOR THE FIRE SUPPRESSION
 IN ACCORDANCE WITH NFPA 96-01.PLEASE
 NOTE, ADDITIONAL PERMIT REQUIRED.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE
 CONTACT PATTY KRAUSS AT (561)805-6719.

Review Stop P PLUMBING
Rev No 1 Status F Date 2006-07-29 Cont ID  
Sent By pschmitz Date 2006-07-29 Time 12:34 Rev Time 0.00
Received By pschmitz Date 2006-07-29 Time 12:34 Sent To  
Notes
2006-07-29 00:00:00PAUL SCHMITZ
 [email protected]
 FBC 2004 PLUMBING CODE PLAN REVIEW
 FBC2004 FUEL GAS CODEPLAN REVIEW
 FBC 2004 CH 11, FL ACESSIBILITY CODE
 AMENDMENTS TO THE FLORIDA BUILDING CODE
  
 CHAPT.1, ADMINISTRATION, 2004 EDITION
  
  
 UNSAT
  
 1)PLANS SHALL BE ROUTED TO DBPR
 BUSINESS AND HOTEL DIVISION FOR
 REVIEW. MINIMUM 2 SETS OF PLANS
 SHALL BE REVIEWED AND STAMPED
 AND THE TWO PAGE ?WORKSHEETS?
 ATTACHED TO EACH SET OF PLANS
 PRIOR TO RESUBMITTING TO CITY OF WEST
 PALM BEACH
 FOR REVIEW. PLEASE CONTACT DBPR
 AT (850) 487-1395.
  
 2)SEE OTHER PLAN REVIEW COMMENTS, THAT
 MAY EFFECT PLUMBING PLAN REVIEW.
  
 3) SHT P1.1 GREASE TRAPS: REFERENCE TO
 DWG P-3 FOR CALCULATION SIZE OF GREASE
 TRAPS. NOT INCLUDED IN THIS SET, AND NOT
 LISTED IN PLUMBING DRAWING INDEX.
 CONTACT W P BEACHWATERPLANT LAB
 SUPERVISOR,INDUSTRIAL COORDINATOR.
 LYNN MASSON."GREASE TRAP SIZE"
  
 OFFICE 561-822-2271
 E-MAIL [email protected]
  
 4)SHT P3.1 WATER PIPING ISOMETRIC:
 SEC 604.9 WATER HAMMER ARRESTORS, SHALL
 BE INSTALLED AS CLOSE TO POINT OF USE AS
 POSSIBLE. NOT AS AIR CHAMBERS.
  
 5) SHT P3.1 WATER SERVICE: SHOW THE
 LOCATION OF THE BACK FLOW PREVENTER.
  
 6) SHT P3.1 A/C CONDENSATE: TERMINATE AT
 LEAST 12" FROM BUILDING IN A PLANTER,
 DRY WELL, OR STORM DRAIN.
 6) SHT A3.1 ROOF DRAINAGE:SEC 1101.7
 1101.2 WHERE REQUIRED.
 ALL ROOFS, PAVED AREAS, YARDS, COURTS
 AND COURTYARDS SHALL DRAIN INTO A
 SEPARATE STORM SEWER SYSTEM. OR TO AN
 APPROVED PLACE OF DISPOSAL. SEC.1107
 SECTION 1107
 SECONDARY (EMERGENCY) ROOF DRAINS
 1107.1 SECONDARY DRAINAGE REQUIRED.
 SECONDARY (EMERGENCY) ROOF DRAINS OR
 SCUPPERS SHALL BE PROVIDED WHERE THE
 ROOF PERIMETER CONSTRUCTION EXTENDS
 ABOVE THE ROOF IN SUCH A MANNER THAT
 WATER WILL BE ENTRAPPED IF THE PRIMARY
 DRAINS ALLOW BUILDUP FOR ANY REASON.
 1107.2 SEPARATE SYSTEMS REQUIRED.
 SECONDARY ROOF DRAIN SYSTEMS SHALL HAVE
 THE END POINT OF DISCHARGE SEPARATE FROM
 THE PRIMARY SYSTEM. DISCHARGE SHALL BE
 ABOVE GRADE, IN A LOCATION WHICH WOULD
 NORMALLY BE OBSERVED BY THE BUILDING
 OCCUPANTS OR MAINTENANCE PERSONNEL.
 1107.3 SIZING OF SECONDARY DRAINS.
 SECONDARY (EMERGENCY) ROOF DRAIN SYSTEMS
 SHALL BE SIZED IN ACCORDANCE WITH
 SECTION 1106 BASED ON THE RAINFALL RATE
 FOR WHICH THE PRIMARY SYSTEM IS SIZED IN
 TABLES 1106.2, 1106.3 AND 1106.6.
 SCUPPERS SHALL BE SIZED TO PREVENT THE
 DEPTH OF PONDING WATER FROM EXCEEDING
 THAT FOR WHICH THE ROOF WAS DESIGNED AS
 DETERMINED BY SECTION 1101.7. SCUPPERS
 SHALL NOT HAVE AN OPENING DIMENSION OF
 LESS THAN 4 INCHES (102 MM). THE FLOW
 THROUGH THE PRIMARY SYSTEM SHALL NOT BE
 CONSIDERED WHEN SIZING THE SECONDARY
 ROOF DRAIN SYSTEM
 7) SEPERATE PERMITS FOR DEMOLITION,
 PLUMBING, GAS PIPING.
 8) DISCRIPTION OF WORK ON COVER SHT T1.0
 STATES THIS IS HURRICANE DAMAGE REPAIR
 WORK. THIS IS A ALTERATION. PLEASE
 REVISE SHT. T1.0 TO REFLECT THE SCOPE OF
 WORK IN THIS SET OF PLANS.
  
 END OF COMMENTS,QUESTIONS 561-805-6692