Plan Review Details - Permit 05121154
| Plan Review Stops For Permit 05121154 |
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2006-03-31 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2006-03-31 |
Time |
10:38 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2006-03-31 |
Time |
10:38 |
Sent To |
ENG |
|
| Notes |
| 2006-03-31 00:00:00 | TO "ENG" BOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2006-03-24 |
|
|
Cont ID |
|
| Sent By |
spalmer |
Date |
2006-03-24 |
Time |
17:44 |
Rev Time |
0.00 |
| Received By |
spalmer |
Date |
2006-03-24 |
Time |
17:44 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2006-03-07 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2006-03-07 |
Time |
15:24 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2006-03-07 |
Time |
15:24 |
Sent To |
Z |
|
| Notes |
| 2006-03-07 00:00:00 | TO "Z" BOX/RESUB |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2006-03-07 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2006-01-11 |
Time |
15:23 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2005-12-28 |
Time |
10:43 |
Sent To |
|
|
| Notes |
| 2005-12-28 00:00:00 | TO "Z" BOX |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
4 |
Status |
P |
Date |
2006-03-29 |
|
|
Cont ID |
|
| Sent By |
jroach |
Date |
2006-03-29 |
Time |
11:19 |
Rev Time |
0.00 |
| Received By |
jroach |
Date |
2006-03-29 |
Time |
11:19 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
3 |
Status |
F |
Date |
2006-03-28 |
|
|
Cont ID |
|
| Sent By |
mmclean |
Date |
2006-03-28 |
Time |
11:42 |
Rev Time |
0.00 |
| Received By |
mmclean |
Date |
2006-03-28 |
Time |
11:42 |
Sent To |
|
|
| Notes |
| 2006-03-28 00:00:00 | DENIED, | | | 1. TOO MUCH CONCRETE WITHIN THE FRONT | | | SETBACK OF THE PROPERTY. | | | 2. NEED TO REDUCE THE DRIVEWAY TO MEET | | | THE REQUIREMENT OF 75% OF LANDSCAPE | | | WITHIN THE FIRST 25FT FRONT SETBACK. | | | | | | NOTE: MUST MAINTAIN 1000SQ FT OR 75% | | | WHICHEVER IS LESS WITHIN THE FIRST 25FT | | | FRONT SETBACK. | | | | | | 3. CAN ONLY HAVE 11.5FT OF CONCRETE | | | WITHIN THE 25FT FRONT SETBACK. | | | | | | MICHELLE MCLEAN | | | ZONING TECHNICIAN | | | 805-6720 |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
F |
Date |
2006-03-14 |
|
|
Cont ID |
|
| Sent By |
mmclean |
Date |
2006-03-14 |
Time |
13:27 |
Rev Time |
0.00 |
| Received By |
mmclean |
Date |
2006-03-14 |
Time |
13:27 |
Sent To |
|
|
| Notes |
| 2006-03-14 00:00:00 | DENIED, | | | 1. THE PROPOSED DRIVEWAY IS OVER THE | | | REQUIRED AMOUNT OF CONCRETE THAT ALLOWED | | | WITHIN THE FIRST 25FT FRONT SETBACK. | | | 2. CAN ONLY HAVE 298.75SQ FT (11.5FT | | | WIDE) OF PAVERS WITHIN THE FIRST 25FT | | | FRONT SETBACK. | | | | | | | | | MICHELLE MCLEAN | | | ZONING TECHNICIAN | | | 805-6720 |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2006-01-11 |
|
|
Cont ID |
|
| Sent By |
mmclean |
Date |
2006-01-11 |
Time |
13:51 |
Rev Time |
0.00 |
| Received By |
mmclean |
Date |
2006-01-11 |
Time |
13:51 |
Sent To |
|
|
| Notes |
| 2006-01-11 00:00:00 | DENIED, | | | 1. MUST PROVIDE TWO COPY OF CURRENT | | | SURVEY SHOWING THE WHOLE STRUCTURE, | | | DIMENSION OF LOT WITH SETBACK OF THE | | | STRUCTURE ON THE PROPERTY | | | 2. NEED TO PROVIDE THE DIMENISON OF THE | | | EXISTING DRIVEWAY AND THE PROPOSED ON | | | THE TWO CURRENT COPY OF SURVEY. | | | 3. CANNOT USE RIVER ROCK, MUST BE A | | | SMOOTH NON-DUSTING SURFACE (ASPHALT, | | | PAVERS, CONCRETE). | | | | | | NOTE: MUST MAINTAIN 1000SQ FT OR 75% OF | | | LANDSCAPE, WHICHEVER IS LESS WITHIN THE | | | FIRST 25FT FRONT SETBACK. | | | | | | MICHELLE MCLEAN | | | ZONING TECHNICIAN | | | 805-6720 |
|
|
|