| Plan Review Stops For Permit 05090332 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2005-09-19 |
|
|
Cont ID |
|
| Sent By |
jwitmer |
Date |
2005-09-19 |
Time |
13:06 |
Rev Time |
1.33 |
| Received By |
jwitmer |
Date |
2005-09-19 |
Time |
13:06 |
Sent To |
PC |
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2005-09-16 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2005-09-16 |
Time |
12:11 |
Rev Time |
0.75 |
| Received By |
dpalmer |
Date |
2005-09-16 |
Time |
12:11 |
Sent To |
|
|
| Notes |
| 2005-09-16 00:00:00 | ******** PROVISO/ REVISION ********* | | | | | | 1)NOTE: PLEASE SEE 450.3(B) FOR MAX | | | OVER-CURRENBT PROTECTION FOR 45KVA | | | TRANSFORMER. 125%) PLEASE SEE 100A BRKR | | | SHOWN. | | | | | | 2)NOTE: PLEASE SEE FEEDS TO BOTH | | | TRANSFOMERS CONTAIN NEUTRALS. PLEASE SEE | | | THESE SYSTEMS SEEM TO BE BOTH SEPARATELY | | | DERIVED SYSTEMS. | | | 450 | | | | | | PLEASE REVISE THE ABOVE INFORMATION | | | ALONG WITH ANY OTHER REVISIONS BEFORE | | | THE ROUGH ELECTRICAL INSPECTION. | | | | | | IF THERE ARE ANY QUESTIONS, PLEASE DO | | | NOT HESITATE IN CONTACTING THIS OFFICE. | | | | | | DEWEY PALMER | | | ELECTRICAL PLAN REVIEW | | | 561-805-6717 | | | [email protected] |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2005-09-16 |
|
|
Cont ID |
|
| Sent By |
mwennerg |
Date |
2005-09-16 |
Time |
14:19 |
Rev Time |
0.00 |
| Received By |
mwennerg |
Date |
2005-09-16 |
Time |
14:19 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2006-01-12 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2006-01-12 |
Time |
11:24 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2006-01-12 |
Time |
11:24 |
Sent To |
M |
|
| Notes |
| 2006-01-12 00:00:00 | TO "M" BOX/REV |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2005-09-21 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2005-09-21 |
Time |
17:31 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2005-09-21 |
Time |
17:31 |
Sent To |
P |
|
| Notes |
| 2005-09-21 00:00:00 | TO "P" BOX/RESUB |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2005-09-19 |
|
|
Cont ID |
|
| Sent By |
jwitmer |
Date |
2005-09-19 |
Time |
13:06 |
Rev Time |
0.00 |
| Received By |
jwitmer |
Date |
2005-09-13 |
Time |
09:45 |
Sent To |
|
|
| Notes |
| 2005-09-13 00:00:00 | TO "BOB"#5 |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
P |
Date |
2006-01-12 |
|
|
Cont ID |
|
| Sent By |
tgordon |
Date |
2006-01-12 |
Time |
14:17 |
Rev Time |
0.25 |
| Received By |
tgordon |
Date |
2006-01-12 |
Time |
14:17 |
Sent To |
|
|
| Notes |
| 2006-01-12 00:00:00 | REVISION TO MECH. PLANS PAGE M-1 . |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
P |
Date |
2005-09-19 |
|
|
Cont ID |
|
| Sent By |
hmoser |
Date |
2005-09-19 |
Time |
10:27 |
Rev Time |
0.00 |
| Received By |
hmoser |
Date |
2005-09-19 |
Time |
10:04 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
MEDGAS |
MEDICAL GAS |
| Rev No |
2 |
Status |
P |
Date |
2005-09-22 |
|
|
Cont ID |
|
| Sent By |
jleech |
Date |
2005-09-22 |
Time |
10:58 |
Rev Time |
1.00 |
| Received By |
jleech |
Date |
2005-09-22 |
Time |
10:58 |
Sent To |
|
|
| Notes |
| 2005-09-22 00:00:00 | PROVISO; | | | 1. VACUUM PUMP EXHAUST AIR MUST BE PIPED | | | SEPARATE TO OUTSIDE, PER NFPA 4-5.2.1.4. | | | AND FBC-2001 MECHANICAL SEC 501.2. | | | 2.MANUFACTURE INSTALLATION INSTRATIONS | | | TO BE ON JOB SIGHT FOR INSPECTORS | | | REVIEW. | | | IF ANY QUESTIONS PLEASE CALL ME; | | | JOHN LEECH | | | 805-6695 |
|
|
| Review Stop |
MEDGAS |
MEDICAL GAS |
| Rev No |
1 |
Status |
F |
Date |
2005-09-17 |
|
|
Cont ID |
|
| Sent By |
jleech |
Date |
2005-09-17 |
Time |
09:45 |
Rev Time |
1.50 |
| Received By |
jleech |
Date |
2005-09-17 |
Time |
09:45 |
Sent To |
|
|
| Notes |
| 2005-09-17 00:00:00 | MED-GAS DENIED; | | | 1 | | | CONTRACTOR INSTALLING AIR AND VACUUM | | | SYSTEM MUST BE LICENSED TO INSTALL | | | MEDICAL GAS. (ADD TO NOTES) | | | 2.VACUUM PIPING SHALL COMPLY WITH NFPA | | | PP-C SEC. 4-5.2.2.1 (CLEANOUTS REQUIRED) | | | 3.AIR VENT FOR MAKE-UP AIR FOR | | | COMPRESSOR SHOWN ON SHEET A-2 IS NOT | | | SHOWN ON MECH. DRAWINGS. SHOWS SIZE AND | | | WHERE MAKE-UP ORIGINATES FROM. | | | 4.EXHAUST FROM THE VACUUM SYSTEM SHALL | | | BE PIPED TO THE OUTSIDE PER. NFPA 99-C | | | SEC. 4-52.1.4 (SHOW ON DRAWINGS) | | | 5.DENTAL EQUIPMENT INSTALLATION | | | INSTRUCTIONS ARE NOT WITH PLANS. PLEASE | | | SUBMIT FOR REVIEW. | | | 6.FLOOR DRAIN IN EQUIPMENT ROOM SHOULD | | | HAVE A TRAP PRIMER. | | | MED-GAS PLAN REVIEW BY; | | | JOHN LEECH | | | 805-6695 |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2005-09-17 |
|
|
Cont ID |
|
| Sent By |
jleech |
Date |
2005-09-17 |
Time |
09:20 |
Rev Time |
1.00 |
| Received By |
jleech |
Date |
2005-09-17 |
Time |
09:20 |
Sent To |
|
|
| Notes |
|
|