| Plan Review Stops For Permit 05080390 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2005-09-07 |
|
|
Cont ID |
|
| Sent By |
alange |
Date |
2005-09-07 |
Time |
13:03 |
Rev Time |
0.50 |
| Received By |
alange |
Date |
2005-09-07 |
Time |
13:00 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2005-08-24 |
|
|
Cont ID |
|
| Sent By |
alange |
Date |
2005-08-24 |
Time |
13:42 |
Rev Time |
0.33 |
| Received By |
alange |
Date |
2005-08-24 |
Time |
13:42 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
3 |
Status |
P |
Date |
2005-09-19 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2005-09-19 |
Time |
15:47 |
Rev Time |
1.00 |
| Received By |
dpalmer |
Date |
2005-09-19 |
Time |
15:47 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
F |
Date |
2005-09-03 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2005-09-03 |
Time |
11:39 |
Rev Time |
0.50 |
| Received By |
dpalmer |
Date |
2005-09-03 |
Time |
11:39 |
Sent To |
M |
|
| Notes |
| 2005-09-03 00:00:00 | ************* UNSAT *********** | | | | | | 1)NOTE: PLEASE SEE PLANS INDICATE | | | RE-FEEDING THE ENTIRE SERVICE. PLEASE | | | PROVIDE LOADS CALCULATIONS PER 220.31B | | | | | | | | | PLEASE SEE SPECS INDICATE THIS UNIT | | | RATED 167A'S WITH LP AS THE PRIME MOVER. | | | PLEASE SEE NATURAL GAS IS BEING USED AND | | | GENERATED IS NOT RATED FOR THE SAME | | | AMERAGE. | | | PLEASE PROVIDE LOAD CALCS AS ABOVE FOR | | | INTENDED LOADS. | | | PLEASE KNOW, IF AUTOMATIC LOAD SHEEDING | | | OF "HEAT" ON A/C SYSTEMS IS | | | NOTED/DETAILED AND PROVIDE. HEAT LOAD | | | AND AND ANY OTHER "SHEDDED" ITEMS MAY BE | | | REMOVED FROM LOAD CACULATIONS. | | | 215.5,700.5, 702.5 | | | | | | 2)NOTE: PLEASE SEE GEN SPEC SHEETS | | | SUBMITTED SHOWS ARROW TO 40KW UNIT, | | | HOWEVER NG CIRCILED FOR 30KW ALSO? | | | | | | PLEASE SUBMIT THE ABOVE INFORMATION FOR | | | REVIEW. IF THERE ARE ANY QUESTIONS, | | | PLEASE DO NOT HESITATE TO CALL. | | | | | | DEWEY PALMER | | | ELECTRICAL PLAN REVIEW | | | CITY OF WEST PALM BEACH | | | CONSTUCTION SERVICES DEPT. | | | 561-805-6717 | | | [email protected] | | | | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
F |
Date |
2005-08-18 |
|
|
Cont ID |
|
| Sent By |
btrobaug |
Date |
2005-08-18 |
Time |
14:13 |
Rev Time |
0.50 |
| Received By |
btrobaug |
Date |
2005-08-18 |
Time |
14:04 |
Sent To |
M |
|
| Notes |
| 2005-08-18 00:00:00 | | | | PLEASE SUBMIT A SITE PLAN INDICATING THE | | | LOCATION OF ALL SERVICE AND GENERATOR | | | EQUIPMENT SO THAT COMPLIANCE WITH 225.31 | | | THROUGH 225.37 CAN BE DETERMINED. | | | | | | THE RISER DIAGRAM IS INCOMPLETE.(UNLESS | | | THE TRANSFER SWITCH IS ALSO THE PANEL). | | | | | | IF THERE ARE ANY QUESTIONS PLEASE CALL. | | | | | | BILL TROBAUGH | | | ELECTRICAL PLAN REVIEW | | | 561/805-6718 | | | [email protected] | | | FAX/:561/659-8026 | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2005-09-15 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2005-09-15 |
Time |
16:46 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2005-09-15 |
Time |
16:46 |
Sent To |
E |
|
| Notes |
| 2005-09-15 00:00:00 | TO "DPALMER" DESK/RESUB |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2005-09-01 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2005-09-01 |
Time |
16:45 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2005-09-01 |
Time |
16:45 |
Sent To |
E |
|
| Notes |
| 2005-09-01 00:00:00 | TO "DPALMER" DESK/RESUB |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2005-08-17 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2005-08-17 |
Time |
09:12 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2005-08-17 |
Time |
09:12 |
Sent To |
E |
|
| Notes |
| 2005-08-17 00:00:00 | TO "E" BOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2005-09-01 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2005-08-24 |
Time |
16:45 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2005-08-09 |
Time |
09:28 |
Sent To |
|
|
| Notes |
| 2005-08-09 00:00:00 | TO "G" BOX |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
P |
Date |
2005-09-07 |
|
|
Cont ID |
|
| Sent By |
prafter |
Date |
2005-09-07 |
Time |
11:16 |
Rev Time |
0.75 |
| Received By |
prafter |
Date |
2005-09-07 |
Time |
11:16 |
Sent To |
B |
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
F |
Date |
2005-08-24 |
|
|
Cont ID |
|
| Sent By |
prafter |
Date |
2005-08-24 |
Time |
10:29 |
Rev Time |
1.50 |
| Received By |
prafter |
Date |
2005-08-24 |
Time |
10:29 |
Sent To |
B |
|
| Notes |
| 2005-08-24 00:00:00 | MECH. PLAN REVIEW: | | | | | | 1. GENERATOR MANF. RECOMBINATIONS FOR | | | SERVICE CLEARANC /VENILATION IN | | | FEET/INCHES IN ALL DIRECTION MUST ACCOM. | | | GENERATOR PERMIT APP.NEC 70 110.3 B. | | | | | | 2.GENERATOR EXHAUST MUST BE TEN FEET | | | AWAY FROM ANY BUILDING OPENING, AND | | | EXHAUST MUST BE DIRECTED AWAY FROM | | | BUILDING.AND BE TEN FEET FROM PROPETY | | | LINE.2001 FBC/M 804.3.3 TERMINATION. | | | 2001 FBC/M SECTION 915 8.2.3.2 | | | EXHAUST SYSTEM TERMINATION. | | | | | | 3. LP/NAT GAS REQUIRES PERMIT, FROM | | | LICENSED GAS CONTRACTOR. | | | | | | PAT RAFTER 561/805/6728 OR 805/6719 | | | PATTY KRAUSS. | | | | | | PLEASE CALL IF THEAR ANY QUESTIONS. |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
N |
Date |
2005-08-13 |
|
|
Cont ID |
|
| Sent By |
jleech |
Date |
2005-08-13 |
Time |
13:45 |
Rev Time |
0.00 |
| Received By |
jleech |
Date |
2005-08-13 |
Time |
13:45 |
Sent To |
Z |
|
| Notes |
| 2005-08-13 00:00:00 | PERMIT FOR NATURAL GAS REQUIRED BEFORE | | | FINAL INSPECTION ON GENERATOR. |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2005-08-16 |
|
|
Cont ID |
|
| Sent By |
mmclean |
Date |
2005-08-16 |
Time |
16:26 |
Rev Time |
0.00 |
| Received By |
mmclean |
Date |
2005-08-16 |
Time |
16:26 |
Sent To |
I |
|
| Notes |
|
|