| 2005-09-07 00:00:00 | BUILDING REVIEW THIRD CHECKLIST: |
| | 1- STILL UNABLE TO PERFORM PLAN REVIEW |
| | TO VERIFY COMPLIANCE OF PRODUCT USE IF |
| | COMPLETE INSTALLATION INFORMATION IS NOT |
| | PROVIDED. |
| | CONTRACTOR WAS ASKED TO MARK ON DRAWINGS |
| | SPECIFIC MOUNTING CONDITIONS AND ANCHOR |
| | TYPE AND SPACING TO BE USED ACCORDING TO |
| | THE DESIGN PRESSURES, EDGE DISTANCE, |
| | PANEL SPAN, CONNECTION TYPE AND |
| | STRUCTURE TO BE ATTACHED TO (CONCRETE, |
| | CONCRETE BLOCK OR WOOD). SECTION |
| | 104.2.1.2 CITY AMENDMENTS TO THE FBC |
| | 2001 AND THE CITY IMPLEMENTATION |
| | STANDARD FOR HURRICANE MISSILE IMPACT |
| | PROTECTION. IN ADDITION ANCHOR NOTE #2 |
| | ON PAGE 5 OF 5 OF THE ACCORDION DRAWINGS |
| | CALLS FOR THE SAME INFORMATION I |
| | REQUESTED ON THE FIRST CHECKLIST. |
| | |
| | BY PROVIDING THIS SIMPLE INFORMATION |
| | PLAN REVIEWER CAN VERIFY THAT PROPER |
| | ANCHOR TYPE AND SPACING IS USED. |
| | |
| | INSTALLATION SCHEDULE CALLS FOR TAPCON |
| | AS THE ANCHOR TO BE USED. THE ANCHOR |
| | SCHEDULE IN PAGE 5 OF 5 SHOWS THREE |
| | DIFFERENT TYPES OF TAPCONS. SOME WORK |
| | FOR THE SPACING SPECIFIED IN THE |
| | INSTALLATION SCHEDULE AND SOME DON'T. |
| | THAT'S WHY IS IMPORTANT TO BE SPECIFIC. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CALL |
| | JULIO GOMEZ AT (561)805-6712. |