Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2005-10-06 Cont ID  
Sent By alange Date 2005-10-06 Time 11:23 Rev Time 1.25
Received By alange Date 2005-10-06 Time 09:37 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2005-09-28 Cont ID  
Sent By alange Date 2005-09-28 Time 14:42 Rev Time 0.66
Received By alange Date 2005-09-28 Time 14:39 Sent To  
Notes
2005-09-28 00:00:00DENIED
  
 1. 713.13 F.S.A NOTICE OF COMMENCEMENT
 SHALL BE RECORDED AT PALM BEACH COUNTY
 COURTHOUSE AND A COPY SUBMITTED TO THIS
 OFFICE BEFORE A PERMIT CAN BE ISSUED.
 BLANK FORMS ARE AVAILABLE FROM THIS
 OFFICE.
 NOTE: THE NOTICE OF COMMENCEMENT MUST BE
 RE-RECORDED IF THE DESCRIBED IMPROVEMENT
 OR CONSTRUCTION IS NOT COMMENCED WITHIN
 90 DAYS OF RECORDING.
  
 2.BEFORE A PERMIT TO CONSTRUCT, MAY BE
 ISSUED, IMPACT FEES MUST BE PAID TO PALM
 BEACH COUNTY. THE ACTUAL PERMIT
 SET OF PLANS MUST BE STAMPED BY THAT
 OFFICE, AND A COPY OF THE PAID RECEIPT
 ATTACHED TO THE PERMIT APPLICATION.
 PLEASE CALL (561)233-5025 FOR MORE
 INFORMATION.
  
  
 ANY QUESTIONS CALL ME.
  
 ART LANGE
 BUILDING PLANS EXAMINER
 805-6672
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2005-09-07 Cont ID  
Sent By alange Date 2005-09-07 Time 11:00 Rev Time 1.00
Received By alange Date 2005-09-07 Time 08:28 Sent To  
Notes
2005-09-07 00:00:00DENIED
  
 1. 713.13 F.S.A NOTICE OF COMMENCEMENT
 SHALL BE RECORDED AT PALM BEACH COUNTY
 COURTHOUSE AND A COPY SUBMITTED TO THIS
 OFFICE BEFORE A PERMIT CAN BE ISSUED.
 BLANK FORMS ARE AVAILABLE FROM THIS
 OFFICE.
 NOTE: THE NOTICE OF COMMENCEMENT MUST BE
 RE-RECORDED IF THE DESCRIBED IMPROVEMENT
 OR CONSTRUCTION IS NOT COMMENCED WITHIN
 90 DAYS OF RECORDING.
  
 2.BEFORE A PERMIT TO CONSTRUCT, MAY BE
 ISSUED, IMPACT FEES MUST BE PAID TO PALM
 BEACH COUNTY. THE ACTUAL PERMIT
 SET OF PLANS MUST BE STAMPED BY THAT
 OFFICE, AND A COPY OF THE PAID RECEIPT
 ATTACHED TO THE PERMIT APPLICATION.
 PLEASE CALL (561)233-5025 FOR MORE
 INFORMATION.
  
  
 ANY QUESTIONS CALL ME.
  
 ART LANGE
 BUILDING PLANS EXAMINER
 805-6672
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2005-08-09 Cont ID  
Sent By alange Date 2005-08-09 Time 08:35 Rev Time 3.50
Received By alange Date 2005-08-09 Time 08:35 Sent To  
Notes
2005-08-09 00:00:00DENIED
  
 1. 713.13 F.S.A NOTICE OF COMMENCEMENT
 SHALL BE RECORDED AT PALM BEACH COUNTY
 COURTHOUSE AND A COPY SUBMITTED TO THIS
 OFFICE BEFORE A PERMIT CAN BE ISSUED.
 BLANK FORMS ARE AVAILABLE FROM THIS
 OFFICE.
 NOTE: THE NOTICE OF COMMENCEMENT MUST BE
 RE-RECORDED IF THE DESCRIBED IMPROVEMENT
 OR CONSTRUCTION IS NOT COMMENCED WITHIN
 90 DAYS OF RECORDING.
  
 2.BEFORE A PERMIT TO CONSTRUCT, MAY BE
 ISSUED, IMPACT FEES MUST BE PAID TO PALM
 BEACH COUNTY. THE ACTUAL PERMIT
 SET OF PLANS MUST BE STAMPED BY THAT
 OFFICE, AND A COPY OF THE PAID RECEIPT
 ATTACHED TO THE PERMIT APPLICATION.
 PLEASE CALL (561)233-5025 FOR MORE
 INFORMATION.
  
 3.BASED ON SBCCI BUILDING VALUATION
 DATA THE PERMIT VALUE HAS BEEN REVISED
 TO $431,649.ADDITIONAL PERMIT FEES ARE
 DUE.
  
 ANY QUESTIONS CALL ME.
  
 ART LANGE
 BUILDING PLANS EXAMINER
 805-6672
  
  

Review Stop E ELECTRICAL
Rev No 3 Status P Date 2005-09-22 Cont ID  
Sent By dpalmer Date 2005-09-22 Time 18:29 Rev Time 0.00
Received By dpalmer Date 2005-09-22 Time 17:58 Sent To P
Notes
2005-09-22 00:00:00STAMPED ELECTRICAL PLANS.
  
 REDLINED 210.52H FOR HALLWAY RECEPTS.

Review Stop E ELECTRICAL
Rev No 2 Status F Date 2005-08-31 Cont ID  
Sent By dpalmer Date 2005-08-31 Time 21:32 Rev Time 0.75
Received By dpalmer Date 2005-08-31 Time 21:13 Sent To P
Notes
2005-08-31 00:00:00IN ELEC FOR REVIEW
 ******* UNSAT ********
  
 PLEASE SEE SOME NOTES FROM PREVIOUS AND
 SOME NEW NOTES DUE TO CHANGES IN PLANS.
  
 1)NOTE: PLEASE SEE LOAD CALCUALTIONS FOR
 POOL SUB PANEL WERE REVISED, HOWEVER OCP
 FOR FEED TO PANEL WAS NOT INCREASED?
 PLEASE SEE PANEL "B" STILL SHOWS 2P60A
 BRKR.
 PLEASE ALSO CORRELATE RISER WITH PANEL
 SCHEDULES.
 PLEASE SEE RISER SHOWS POOL PANEL "C"
 BEING FED FROM MCB OUTSIDE PANEL,
 HOWEVER PANEL SCHEDULE FOR INSIDE PANEL
 INDICATES POOL SUB PANEL BEING FED FROM
 INSIDE?
 PLEASE SEE RISER NOW SHOWS #3'S FOR
 INCREASED FEEDERS.
 PLEASE SEE NO PANEL SCHEDULE FOR EITHER
 OUTSIDE 8/16 CIRCUIT PANELS WERE
 SUBMITTED.
 PLEASE SEE RISER ONLY INDICATES THE 150A
 MCB'S.
 PLEASE ADJUST.
 215.5
  
 2)NOTE: PLEASE SEE IRRIGATION PUMP ON
 PLANS, NOT ON PANEL SCHEDULE OR LOADS.
 215.5
  
 3)NOTE: PLEASE SEE PREVIOUS NOTE # 10
 REQUESTED LTR FROM ARCHITECT. PLEASE SEE
 LTR SUBMITTED IS REQUIRED TO BE SEALED
 AND DATED. FS 481.221
 PLEASE ALSO SEE LETTER IS REQUIRED TO BE
 CORRECTLY NOTORIZED AS SET-FORTH UNDER
 FS 117.05 FOR NOTORIES.
 PLEASE SEE MIN INFORMATION REQUIRED.
 THE STAMP AND SIGNATURE IS INSUFFICENT.
  
 4)NOTE: PLEASE SEE RISER SHOWS 3-1/0'S
 AND #6 CONDUCTORS IN A 1" CONDUIT?
 PLEASE SEE TABLE 9 FOR PIPE FILL.
 PLEASE ADJUST.
  
 PLEASE REMOVE ANY OLD/VOIDED SHEETS AND
 ONLY INSERT NEW REVISED SHEETS INTO
 COMPLETE SETS FOR REVIEW AND STAMPING.
 ONE SET OF OLD SHOULD BE SUBMITTED FOR
 REFERENCE.
  
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE DO NOT HESITATE TO CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 CITY OF WEST PALM BEACH
 CONSTUCTION SERVICES DEPT.
 561-805-6717
 [email protected]
  

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2005-07-25 Cont ID  
Sent By dpalmer Date 2005-07-25 Time 08:26 Rev Time 0.75
Received By dpalmer Date 2005-07-22 Time 16:46 Sent To M
Notes
2005-07-25 00:00:00************ UNSAT **************
  
 1)NOTE: PLEASE SEE SOME MISSING RECEPTS
 PER 210.52 FOR 2' OF WALL SPACE. MAST
 BEDRM, CAFE,
  
 2)NOTE: SMOKE DETECTORS ARE REQUIRED
 INSIDE AND OUTSIDE ALL SLEEPING ROOMS.
 ON EACH LEVEL OF A MULTI-LEVEL DWELLING
 UNIT.
 IN CLOSE PROXIMITY OF STAIRWAYS LEADING
 TO FLOORS ABOVE AND IN THE VICINITY OF
 BEDROOMS.
 PLEASE ALSO NOTE, SD'S ARE REQ'D TO BE
 A MIN OF 3' FROM BATHROOM DOORS AND
 KITCHENS.
 ABOVE PER:FBC 905.2, NFPA-72 8-1.4
 PLEASE SEE MISSING SD'S INSIDE/OUTSIDE
 MASTER BEDRM.
  
 3)NOTE: PLEASE SEE PANEL SCHEDULE SHOWS
 A DEDICATED CIRCUIT FOR A WHIRLPOOL GFI,
 HOWEVER THIS RECEPT COULD NOT BE LOCATED
 ON PLANS??
 215.5
  
 4)NOTE: PLEASE SEE "GOLF CART CIRCUIT
 SHOWN ON PANEL SCHEDULE ALSO, WHICH
 COULD NOT BE LOCATED ON PLANS.
 215.5
  
 5)NOTE; PLEASE SEE MISSING EQUIPMENT
 GROUNDING CONDUCTORS FROM MAINS TO SUB
 PANELS.
 250.110,250.24, SIZE PER 250.122
  
 6)NOTE: PLEASE SEE MIN AIC RATING FROM
 CALCULATIONS ARE OVER MIN AIC RATINGS
 SHOWN ON PLANS.
 AIC RATINGS SHALL BE OVER AVAILABLE
 FAULT CURRENT, RATINGS MAY NOT BE LESS.
 110.9, 215.5
  
 7)NOTE: PLEASE SHOW ALL CONTINUOUS LOADS
 ON POOL PANEL @125%. PLEASE SEEE THIS
 WILL AFFECT FEEDER FROM PANEL "B" TO
 POOL PANEL. LOAD IS ALREADY SHOWN AT
 59A'S.
 215.3,230.42,680.9 ETC.
  
 8)NOTE: PLEASE LIST ALL THE REQUIRED ARC
 FAULT PROTECTED CIRCUITS ON PANEL
 SCHEDULE. PLEASE SEE ALL ARC FAULT
 PROTECTION SHALL BE LISTED PER 2002 NEC
 210.12
  
 9)NOTE: PLEASE SEE "WHITE-OUT" ON PLANS
 IS NOT PERMITTED TO PLANS SIGNED AND
 SEALED BY AN ARCHITEC.
 FS 481.221
  
 10)NOTE: PLEASE CLARIFY SIGNED PLANS.
 PLEASE SEEE PLANS APPEAR TO BE SIGNED
 WITH INITIALS? IF INDEED LEGAL SIGNATURE
 FOR ARCHITECT, PLEASE PROVIDE A LETTER
 TO VERIFY LEGAL SIGNATURE. THIS LETTER
 SHALL BE SIGNED, DATED AND SEALED BY
 ARCHITECT. THE LETTER SHOULD ALSO BE
 NOTORIZED UNDER FS 117.
 THIS LTR WILL BE PLACED IN SIGNATURE
 FILE FOR ANY FUTURE VERIFICATION.
  
 PLEASE REMOVE ANY OLD/VOIDED SHEETS AND
 ONLY INSERT NEW REVISED SHEETS INTO
 COMPLETE SETS FOR REVIEW AND STAMPING.
 ONE COPY OF OLD/VOIDED SHEETS SHOULD BE
 SUBMITTED FOR REFERENCE ONLY.
  
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 561-805-6717
 [email protected]
2005-07-22 00:00:00IN ELEC FOR REVIEW

Review Stop I INCOMING/PROCESSING
Rev No 9 Status N Date 2005-12-12 Cont ID  
Sent By adarroug Date 2005-12-12 Time 13:36 Rev Time 0.00
Received By adarroug Date 2005-12-12 Time 13:36 Sent To P
Notes
2005-12-12 00:00:00TO "P" BOX/SUBMITTAL

Review Stop I INCOMING/PROCESSING
Rev No 8 Status N Date 2005-10-07 Cont ID  
Sent By adarroug Date 2005-10-07 Time 11:24 Rev Time 0.00
Received By adarroug Date 2005-10-07 Time 11:24 Sent To P
Notes
2005-10-07 00:00:00TO "P" BOX/SUBMITTAL

Review Stop I INCOMING/PROCESSING
Rev No 7 Status N Date 2005-09-30 Cont ID  
Sent By adarroug Date 2005-09-30 Time 09:06 Rev Time 0.00
Received By adarroug Date 2005-09-30 Time 09:06 Sent To B
Notes
2005-09-30 00:00:00TO "ALANGE" DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2005-09-21 Cont ID  
Sent By adarroug Date 2005-09-21 Time 10:30 Rev Time 0.00
Received By adarroug Date 2005-09-21 Time 10:30 Sent To E
Notes
2005-09-21 00:00:00TO "DPALMER" DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2005-08-29 Cont ID  
Sent By adarroug Date 2005-08-29 Time 09:23 Rev Time 0.00
Received By adarroug Date 2005-08-29 Time 09:23 Sent To E
Notes
2005-08-29 00:00:00TO "DPALMER" DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2005-08-17 Cont ID  
Sent By adarroug Date 2005-08-17 Time 15:06 Rev Time 0.00
Received By adarroug Date 2005-08-17 Time 15:06 Sent To Z
Notes
2005-08-17 00:00:00TO "Z" BOX/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2005-07-22 Cont ID  
Sent By adarroug Date 2005-07-22 Time 13:18 Rev Time 0.00
Received By adarroug Date 2005-07-22 Time 13:18 Sent To E
Notes
2005-07-22 00:00:00TO "SFR" "E"/WITH PLANS IN REVIEW

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2005-07-22 Cont ID  
Sent By adarroug Date 2005-07-22 Time 11:16 Rev Time 0.00
Received By adarroug Date 2005-07-22 Time 11:16 Sent To E
Notes
2005-07-22 00:00:00TO "SFR" "E" BOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2005-08-09 Cont ID  
Sent By alange Date 2005-08-09 Time 08:40 Rev Time 0.00
Received By alange Date 2005-07-14 Time 16:06 Sent To  
Notes
2005-07-14 00:00:00TO "Z" BOX

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2005-07-26 Cont ID  
Sent By prafter Date 2005-07-26 Time 07:44 Rev Time 0.50
Received By prafter Date 2005-07-26 Time 07:44 Sent To P
Notes
***NONE***

Review Stop P PLUMBING
Rev No 5 Status P Date 2006-01-18 Cont ID  
Sent By jleech Date 2006-01-18 Time 08:54 Rev Time 0.33
Received By jleech Date 2006-01-18 Time 08:54 Sent To  
Notes
2006-01-18 00:00:00REVISED SANITARY RISER DIAGRAM.

Review Stop P PLUMBING
Rev No 4 Status F Date 2005-11-30 Cont ID  
Sent By jleech Date 2005-11-30 Time 07:28 Rev Time 0.33
Received By jleech Date 2005-11-30 Time 07:28 Sent To  
Notes
2005-11-30 00:00:00DENIED;
 1.HORIZONTAL DRY VENTS SHALL NOT BE
 INSTALLED, SEC905.3. (BIDET)
 2.L/T CAN NOT DRAIN INTO A BATHROOM
 GROUP. SEC.909.1
 3.DESIGN PROFESSIONAL TITLE BLOCK IS
 REQUIRED ON SEALED PLANS.104.2.2
 PLUMBING PLAN REVIEW BY;
 JOHN LEECH
 805-6695

Review Stop P PLUMBING
Rev No 3 Status P Date 2005-09-26 Cont ID  
Sent By jleech Date 2005-09-26 Time 08:18 Rev Time 0.33
Received By jleech Date 2005-09-26 Time 08:18 Sent To B
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status F Date 2005-09-06 Cont ID  
Sent By jleech Date 2005-09-06 Time 13:49 Rev Time 0.75
Received By jleech Date 2005-09-06 Time 13:49 Sent To B1
Notes
2005-09-06 00:00:00DENIED;
 1.MASTER BATH L/T MUST BE DOWN STREAM OF
 THE BATHROOM GROUP. SEC 909.1.
 2.L/T TO DISCHARGE ABOVE W/M AND
 CLEANOUT SHOULD BE AT 48" AFF.
 3.BATH 2 SHOWER IS NOT VENTED.
 4.BATH 3 SHOWER IS NOT VENTED.
 5.SHOW PIPING FOR FUTURE TRAINING ROOM
 BATH ON RISER DIAGRAM.
 ONE SET OF PLANS MARKED IN RED.
 PLUMBING PLAN REVIEW BY;
 JOHN LEECH
 805-6695

Review Stop P PLUMBING
Rev No 1 Status F Date 2005-07-26 Cont ID  
Sent By jleech Date 2005-07-26 Time 10:02 Rev Time 0.50
Received By jleech Date 2005-07-26 Time 09:37 Sent To B
Notes
2005-07-26 00:00:00DENIED;
 1.SANITARY RISER DIAGRAM IS NOT
 COMPLETE. MISSING ONE KITCHEN SINK AND 2
 LAUNDRY TUBS.
 2.BATHROOM #2 SHOWER IS NOT VENTED.
 3.MASTER BATHROOM BITET IS NOT VENTED.
 4.PLEASE SHOW THE FUTURE TRAINING ROOM
 BATHROOM ON THE RISER DIAGRAM SINCE THE
 PLUMBING MUST BE INSTALLED UNDER THE
 SLAB.
 5. PAGE A4 "FIXTURE CONNECTION SCHEDULE"
 AUTOMATIC CLOTHS WASHER SHALL HAVE A 2"
 TRAP. TABLE 709.1.
 PLUMBING PLAN REVIEW BY;
 JOHN LEECH
 805-6695

Review Stop Z ZONING
Rev No 2 Status P Date 2005-08-23 Cont ID  
Sent By mmclean Date 2005-08-23 Time 18:20 Rev Time 0.00
Received By mmclean Date 2005-08-23 Time 18:20 Sent To I
Notes
2005-08-23 00:00:00NOTE: HEIGHT OF CHIMENY/HOUSE MUST BE
 MAX HEIGHT OF 33FT.
  
 NOTE: MUST PULL A SEPERATE FOR
 POOL/SPA/DECK.

Review Stop Z ZONING
Rev No 1 Status F Date 2005-07-21 Cont ID  
Sent By mmclean Date 2005-07-21 Time 16:25 Rev Time 0.00
Received By mmclean Date 2005-07-21 Time 16:25 Sent To I
Notes
2005-07-21 00:00:00DENIED,
 1. STRUCTURE IS OVER THE HEIGHT
 REQUIREMENT FOR ZONING.ALLOWABLE
 HEIGHT IS 30FT WITH 10% FOR CHIMNEY,
 TOTAL 33FT. HEIGHT SHOWING ON ELEVATION
 IS 34+FT.
  
 MICHELLE MCLEAN
 ZONING TECHNICIAN
 805-6720