Plan Review Details - Permit 05051568
Plan Review Stops For Permit 05051568
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2005-07-07 Cont ID  
Sent By lsmith Date 2005-07-07 Time 14:42 Rev Time 0.75
Received By lsmith Date 2005-07-07 Time 14:42 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2005-06-11 Cont ID  
Sent By pschmitz Date 2005-06-11 Time 11:59 Rev Time 0.00
Received By pschmitz Date 2005-06-11 Time 11:59 Sent To PC
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2005-06-28 Cont ID  
Sent By dpalmer Date 2005-06-28 Time 07:48 Rev Time 0.10
Received By dpalmer Date 2005-06-28 Time 07:48 Sent To B
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2005-06-08 Cont ID  
Sent By dpalmer Date 2005-06-08 Time 12:51 Rev Time 0.30
Received By dpalmer Date 2005-06-08 Time 12:51 Sent To P
Notes
2005-06-08 00:00:00*********UNSAT **********
  
 1)NOTE: PLEASE SEE WIRING DIAGRAM
 SUBMITTED SHOWS A RISER DIAGRAM FOR A
 NEW SERVICE. IF A NEW SERVICEIS GOING TO
 BE INSTALLED, THIS MUST BE UNDER A
 SEPARATE PERMIT.
 PLEASE ONLY SUBMIT THE ELECTRICAL WIRING
 DIAGRAM RELATIVE TO POOL.
 IF NEW POOL PANEL IS BEING INSTALLED,
 THEN PLEASE INCLUDE OCP FROM EXISTING
 PANEL(IF EXSITNG) SIZE OF SERVICE ETC.
 PLEASE CLARIFY TYPE OF CONDUIT TO SUB
 PANEL.
 PLEASE SEE TYOE OF CONDUIT APPROVED FOR
 USE AND INSTALLATIONS. ENMT?
  
 2)NOTE: PLEASE SEE THE NUMBER OS
 CONDUCTORS FROM MAIN PANEL TO SUB PANEL.
  
 THIS SEEMS TO BE MISSING EITHER THE
 NUETRAL OER EQUIPMENT GROUNDING??
 250.110,250.24, ETC.
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE DO NOT HESITATE TO CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 561-805-6717
 [email protected]

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2005-06-23 Cont ID  
Sent By adarroug Date 2005-06-23 Time 11:28 Rev Time 0.00
Received By adarroug Date 2005-06-23 Time 11:28 Sent To E
Notes
2005-06-23 00:00:00TO "DPALMER" DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2005-06-06 Cont ID  
Sent By mjacobs Date 2005-06-06 Time 16:40 Rev Time 0.00
Received By mjacobs Date 2005-06-06 Time 16:39 Sent To E
Notes
2005-06-06 00:00:00TO 'E' BOX. POOL

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2005-05-24 Cont ID  
Sent By adarroug Date 2005-05-24 Time 19:09 Rev Time 0.00
Received By adarroug Date 2005-05-24 Time 19:09 Sent To Z
Notes
2005-05-24 00:00:00TO "Z" BOX

Review Stop P PLUMBING
Rev No 1 Status P Date 2005-06-11 Cont ID  
Sent By pschmitz Date 2005-06-11 Time 11:58 Rev Time 0.00
Received By pschmitz Date 2005-06-11 Time 11:58 Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date   Cont ID  
Sent By   Date 2005-06-03 Time   Rev Time  
Received By   Date 2005-06-03 Time   Sent To I
Notes
***NONE***