Plan Review Details - Permit 05042216
Plan Review Stops For Permit 05042216
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2005-08-22 Cont ID  
Sent By alange Date 2005-08-22 Time 10:25 Rev Time 1.75
Received By alange Date 2005-08-22 Time 08:32 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2005-07-28 Cont ID  
Sent By alange Date 2005-07-28 Time 13:39 Rev Time 1.00
Received By alange Date 2005-07-28 Time 13:14 Sent To  
Notes
2005-07-28 00:00:00DENIED
  
  
 1. FBC* 104.6.5BUILDING PERMIT
 VALUATION.THE STATED VALUE OF THE
 PROJECT HAS BEEN UNDER-ESTIMATED AT
 $185,220.THE VALUE, CALCULATED USING
 THE SOUTHERN BUILDING CODE CONGRESS
 INTERNATIONAL (SBCCI) VALUATION TABLES,
 IS $268,860.THE PERMIT APPLICATION FEE
 HAS BEEN ADJUSTED ACCORDINGLY, SO THERE
 IS AN OUTSTANDING BALANCE OF $844.77.
 THE REQUIRED AMOUNT SHALL BE PAID BEFORE
 THE PLANS CAN BE RESUBMITTED.
  
 2.IF BBQ IS TO BE REMOVED FROM PROJECT
 PLEASE REMOVE OFF ALL PAGES.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE
 THE REVISION & REMOVE & REPLACE ANY
 PAGES AS NECESSARY AND SUBMIT ONE SET OF
 OLD PAGES FOR COMPARISON. A TRANSMITTAL
 LETTER LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER, WITH A DESCRIPTION OF
 THE REVISION MADE, IDENTIFYING THE SHEET
 OR SPECIFICATION PAGE WHERE THE CHANGES
 CAN BE FOUND WILL HELP TO EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 ART LANGE
 BUILDING PLANS EXAMINER
 805-6672
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2005-05-19 Cont ID  
Sent By alange Date 2005-05-19 Time 09:21 Rev Time 3.00
Received By alange Date 2005-05-18 Time 16:47 Sent To  
Notes
2005-05-19 00:00:00DENIED
  
  
 1. FBC* 104.6.5BUILDING PERMIT
 VALUATION.THE STATED VALUE OF THE
 PROJECT HAS BEEN UNDER-ESTIMATED AT
 $185,220.THE VALUE, CALCULATED USING
 THE SOUTHERN BUILDING CODE CONGRESS
 INTERNATIONAL (SBCCI) VALUATION TABLES,
 IS $268,860.THE PERMIT APPLICATION FEE
 HAS BEEN ADJUSTED ACCORDINGLY, SO THERE
 IS AN OUTSTANDING BALANCE OF $844.77.
 THE REQUIRED AMOUNT SHALL BE PAID BEFORE
 THE PLANS CAN BE RESUBMITTED.
  
 2.SUBMIT 2 COPIES OF MANUFACTURERS
 SPECS FOR BUILT-INBBQ.
  
 3. FBC 1707.4.4.2SHOW BUCK DETAIL
 COMPLYING WITH THIS SECTION.BUCK SHALL
 HAVE FULL SUPPORT OF THE FRAME.
  
 4. 1 OF A/7 FINISH GRADE FBC 1804.1.7
 WPB AMMENDMENTS FINISHED FLOOR SHALL BE
 4" ABOVE GRADE MINIMUM.
 THE BOTTOM OF FOUNDATION SHALL EXTEND NO
 LESS THAN 12" BELOW GRADE. FBC 1804.2.3
 THESE ARE BOTH MINIMUMS. THIS LEAVES NO
 ROOM FOR ERROR OF THE FINISHED GRADE.
  
 5.MIAMI-DADE PRODUCT APPROVAL FOR PGT
 640 WINDOW DOES NOT GO WITH THE STATE
 APPROVAL SUBMITTED.PLEASE SUBMIT THE
 CORRECT ATATE APPROVAL FOR THIS PRODUCT.
  
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE
 THE REVISION & REMOVE & REPLACE ANY
 PAGES AS NECESSARY. A TRANSMITTAL LETTER
 LISTING THE ORIGINAL REVIEW COMMENT NUM-
 BER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICA
 TION PAGE WHERE THE CHANGES CAN BE FOUND
 WILL HELP TO EXPEDITE YOUR PERMIT. THANK
 YOU FOR YOUR ANTICIPATED COOPERATION.
  
 ART LANGE
 BUILDING PLANS EXAMINER
 805-6672
  
  

Review Stop E ELECTRICAL
Rev No 4 Status P Date 2006-03-10 Cont ID  
Sent By btrobaug Date 2006-03-10 Time 09:14 Rev Time 0.50
Received By btrobaug Date 2006-03-10 Time 08:42 Sent To PC
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 3 Status P Date 2006-01-20 Cont ID  
Sent By dpalmer Date 2006-01-20 Time 20:40 Rev Time 0.00
Received By dpalmer Date 2006-01-20 Time 20:31 Sent To  
Notes
2006-01-20 00:00:00REV'S

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2005-06-27 Cont ID  
Sent By btrobaug Date 2005-06-27 Time 07:12 Rev Time 0.33
Received By btrobaug Date 2005-06-27 Time 06:59 Sent To M
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2005-05-10 Cont ID  
Sent By btrobaug Date 2005-05-10 Time 07:21 Rev Time 0.75
Received By btrobaug Date 2005-05-10 Time 06:18 Sent To M
Notes
2005-05-10 00:00:00 
 PLEASE MAKE THE FOLLOWING CORRECTIONS
 FOR CODE COMPLIANCE AND RESUBMIT FOR
 REVIEW.
  
 1} INDICATE THE LOCATION OF PANEL "B".
  
 2} INDICATE LOCATION OF OVERCURRENT
 PROTECTION FOR PANELS "A" & "B".
  
 3} THE OCP FOR CIRCUITS 12,13 PANEL "A",
 12,13,14,15 PANEL "B" IS TOO LARGE FOR
 THE CONDUCTORS PER 210.16.
  
 4} THE POWDER ROOM REQUIRES A GFI
 RECEPTACLE PER 210.8(A) & 210.52(D).
  
 IF THERE ARE ANY QUESTIONS PLEASE CALL.
  
 BILL TROBAUGH
 ELECTRICAL PLAN REVIEW
 561/805-6718
 [email protected]
 FAX/:561/659-8026

Review Stop I INCOMING/PROCESSING
Rev No 7 Status N Date 2006-03-09 Cont ID  
Sent By adarroug Date 2006-03-09 Time 15:54 Rev Time 0.00
Received By adarroug Date 2006-03-09 Time 15:54 Sent To E
Notes
2006-03-09 00:00:00TO "BTROBAUG" DESK/REV

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2006-01-17 Cont ID  
Sent By adarroug Date 2006-01-17 Time 17:37 Rev Time 0.00
Received By adarroug Date 2006-01-17 Time 17:37 Sent To E
Notes
2006-01-17 00:00:00TO "BTROBAUG" DESK/REV

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2006-01-17 Cont ID  
Sent By adarroug Date 2006-01-17 Time 14:43 Rev Time 0.00
Received By adarroug Date 2006-01-17 Time 14:43 Sent To G
Notes
2006-01-17 00:00:00TO "P" REV

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2005-08-18 Cont ID  
Sent By adarroug Date 2005-08-18 Time 18:02 Rev Time 0.00
Received By adarroug Date 2005-08-18 Time 18:02 Sent To B
Notes
2005-08-18 00:00:00TO "ALANGE" DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2005-06-24 Cont ID  
Sent By adarroug Date 2005-06-24 Time 16:21 Rev Time 0.00
Received By adarroug Date 2005-06-24 Time 16:21 Sent To E
Notes
2005-06-24 00:00:00TO "BTROBAUG" DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2005-05-09 Cont ID  
Sent By adarroug Date 2005-05-09 Time 10:49 Rev Time 0.00
Received By adarroug Date 2005-05-09 Time 10:49 Sent To E
Notes
2005-05-09 00:00:00TO "SFR" "E"

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2005-04-29 Cont ID  
Sent By adarroug Date 2005-05-19 Time 09:21 Rev Time 0.00
Received By alange Date 2005-04-29 Time 17:57 Sent To  
Notes
2005-04-29 00:00:00TO "Z" BOX

Review Stop M MECHANICAL (A/C)
Rev No 2 Status N Date 2005-07-27 Cont ID  
Sent By pkrauss Date 2005-07-27 Time 10:13 Rev Time 0.20
Received By pkrauss Date 2005-07-27 Time 10:11 Sent To  
Notes
2005-07-27 00:00:00NO MECHANICAL PLANS SUBMITTED FOR
 REVIEW, ONLY ENERGY & MANUAL J
 CALCULATIONS.COUSINS AIR LISTED MECH
 CONTRACTOR.

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2005-05-16 Cont ID  
Sent By prafter Date 2005-05-16 Time 11:57 Rev Time 0.75
Received By prafter Date 2005-05-16 Time 11:57 Sent To P
Notes
2005-05-16 00:00:00MECH. PLAN REVIEW:
  
 NO A/C PLANS OR EQUIPMENT INFORMATION.
  
 COUSINS AIR INC. IS LISTED ON PERMIT
 APP.
  
 PAT RAFTER 561/805/6728 OR 805/6719
 PATTY KRAUSS.
  
 PLEASE CALL IF THEAR ANY QUESTIONS.

Review Stop P PLUMBING
Rev No 1 Status P Date 2005-05-17 Cont ID  
Sent By jleech Date 2005-05-17 Time 17:08 Rev Time 0.33
Received By jleech Date 2005-05-17 Time 17:07 Sent To B1
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2005-05-06 Cont ID  
Sent By mmclean Date 2005-05-06 Time 18:34 Rev Time 0.00
Received By mmclean Date 2005-05-06 Time 18:34 Sent To I
Notes
***NONE***