Plan Review Details - Permit 04080570
Plan Review Stops For Permit 04080570
Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2004-08-30 Cont ID  
Sent By csiegber Date 2004-08-30 Time 10:24 Rev Time 0.00
Received By csiegber Date 2004-08-30 Time 10:24 Sent To P
Notes
2004-08-30 00:00:00TO KS BOX/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2004-08-12 Cont ID  
Sent By csiegber Date 2004-08-12 Time 15:07 Rev Time 0.00
Received By csiegber Date 2004-08-12 Time 15:07 Sent To P
Notes
2004-08-12 00:00:00TO GAS

Review Stop P PLUMBING
Rev No 2 Status P Date 2004-09-23 Cont ID  
Sent By kstevens Date 2004-09-23 Time 12:17 Rev Time 1.00
Received By kstevens Date 2004-09-23 Time 12:17 Sent To  
Notes
2004-09-23 00:00:00 
  
  
  
  
  
  
  
 PER N. MELICK MANUFACTURE INFO
 NOT REQUIRED FOR 1 & 2 FAMILY HOMES.
 JULY 17, 2002 OFFICAL INTERPRETATION.
 THE FIELD INSPECTOR SHALL VERIFY THE
 INSTALLED EQUIPMENT INPUT DOES NOT EX-
 CEED THE PIPE SIZING.
  
 IF DRYER ROOM IS A CONFINED SPACE,
 OPENINGS REQUIRED PER SECTION 304.3.1 0R
 SECTION 304.3.2 SHALL BE INSTALLED.
 MINIMUM 1,750 CUBIC FEET REQUIRED.
  
 IF WATER HEATER ROOM IS A CONFINED SPACE
 OPENINGS REQUIRED PER SECTION 304.3.1 OR
 SECTION 304.3.2 SHALL BE INSTALLED.
 MINIMUM 3750 CUBIC FEET REQUIRED.
  
  
  
  
  
  
  
 ,

Review Stop P PLUMBING
Rev No 1 Status F Date 2004-08-21 Cont ID  
Sent By csiegber Date 2004-08-30 Time 10:24 Rev Time 0.60
Received By kstevens Date 2004-08-21 Time 12:19 Sent To  
Notes
2004-08-21 00:00:00DENIED
 REFERENCE: FBC-2001 FUEL GAS
 FBC-2001 CHAPTER 1
  
 1. SUBMIT AN ISOMETRIC DRAWING THAT
 CLEARLY SHOWS ALL CUT SECTIONS OF PIPE
 AND CORRESPONDING LENGTHS PER FBC-2001
 FUEL GAS CODE. NOT ALL CUT SECTIONS SHOW
 THE LENGTH.
 2. TYPE OF GAS, (LP OR NATURAL)
 3. BTU LOAD OF EACH APPLIANCE AND THE
 TOTAL BTU LOAD ON THE SYSTEM. REFER TO
 THE FBC-2001 FUEL GAS CODE SECS. 401.8
 THRU 402.5.2 AND TABLES 402(1) THRU
 402(34).TOTAL BTU LOAD OF EACH SYSTEM
 IS NOT SHOWN.
 4. SUBMIT CALCULATIONS FOR COMBUSTION
 AIR (IF APPLICABLE) PER FBC-2001 FUEL
 GAS CODE SECTION 304.
 5. INDICATE HOW THE FUTURE GAS PIPING
 WILL BE VALVED AND CAPPED OFF UNTILL THE
 PIPING IS FINISHED. SECTION 104.2.1
 6) ALL DRAWINGS SHALL BEAR THE NAME AND
 SIGNATURE OF THE PERSON RESPONSIBLE FOR
 THE DESIGN. SECTION 104.2.1
  
 REVIEW BY KEN STEVENS
 (561) 805-6721
 FAX (561) 653-2692
 E-MAIL [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved