Plan Review Details - Permit 03060291
Plan Review Stops For Permit 03060291
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2003-07-16 Cont ID  
Sent By dpalmer Date 2003-07-22 Time 10:31 Rev Time 2.50
Received By lhatten Date 2003-07-10 Time 13:47 Sent To  
Notes
2003-07-16 00:00:00REVIEWED & STAMPED PLANS 07/10/2003

Review Stop E ELECTRICAL
Rev No 3 Status P Date 2004-03-09 Cont ID  
Sent By btrobaug Date 2004-03-09 Time 10:56 Rev Time 0.50
Received By btrobaug Date 2004-03-09 Time 10:48 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2003-07-22 Cont ID  
Sent By csiegber Date 2004-03-04 Time 13:39 Rev Time 0.25
Received By dpalmer Date 2003-07-22 Time 10:31 Sent To B
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2003-06-20 Cont ID  
Sent By shernand Date 2003-07-18 Time 09:49 Rev Time 0.25
Received By dpalmer Date 2003-06-20 Time 06:25 Sent To P
Notes
2003-06-20 00:00:00************ UNSAT **************
  
 1)NOTE: PLEASE CORRELATE RISER/PANEL
 SCHEDULES. ONE SHOWS 225A MAIN, AND 200A
 ALSO SHOWN.
 SUB PANEL SHOWN AS 75A ALSO 60A?
  
 2)NOTE: PLEASE SEE NEC, SHOWN AS 251-22,
 CORRECT ART IS 250-122.
  
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 561-805-6717
 [email protected]

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2004-03-04 Cont ID  
Sent By csiegber Date 2004-03-04 Time 13:39 Rev Time 0.00
Received By csiegber Date 2004-03-04 Time 13:39 Sent To E
Notes
2004-03-04 00:00:00TO BT DESK/REV

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2004-01-20 Cont ID  
Sent By csiegber Date 2004-01-20 Time 16:46 Rev Time 0.00
Received By csiegber Date 2004-01-20 Time 16:46 Sent To M
Notes
2004-01-20 00:00:00TO PK BOX/REV

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-07-18 Cont ID  
Sent By shernand Date 2003-07-18 Time 09:49 Rev Time 0.00
Received By shernand Date 2003-07-18 Time 09:49 Sent To E
Notes
2003-07-18 00:00:00DP DESK

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-06-05 Cont ID  
Sent By mmclean Date 2003-06-11 Time 12:47 Rev Time 0.00
Received By shernand Date 2003-06-05 Time 11:43 Sent To Z
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2004-01-26 Cont ID  
Sent By hmoser Date 2004-01-26 Time 18:15 Rev Time 0.50
Received By hmoser Date 2004-01-26 Time 18:15 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2003-06-24 Cont ID  
Sent By csiegber Date 2004-01-20 Time 16:46 Rev Time 0.25
Received By pkrauss Date 2003-06-24 Time 07:25 Sent To P
Notes
2003-06-24 00:00:00PROVISO:MECHANICAL PERMIT 03060252
  
 ENERGY CALCULATIONS INDICATE A 13.7 SEER
 UNIT AND THE EQUIPMENT SCHEDULE ON THE
 PLAN INDICATES A 13 SEER.PLEASE
 CORRECT.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE
 CONTACT PATTY KRAUSS AT (561) 805-6719.

Review Stop P PLUMBING
Rev No 1 Status P Date 2003-06-24 Cont ID  
Sent By pkrauss Date 2003-06-24 Time 07:29 Rev Time 0.33
Received By jleech Date 2003-06-24 Time 17:33 Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2003-06-11 Cont ID  
Sent By shernand Date 2003-06-05 Time 11:43 Rev Time 1.00
Received By mmclean Date   Time   Sent To I
Notes
***NONE***