Plan Review Details - Permit 03051975
Plan Review Stops For Permit 03051975
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2003-07-10 Cont ID  
Sent By jgomez Date 2003-07-10 Time 15:39 Rev Time 0.50
Received By jgomez Date 2003-07-10 Time 15:39 Sent To PC
Notes
2003-07-10 00:00:00STORM SHUTTERS CHECKLIST:
 1-ANCHOR SPACING FOR WOOD ANCHORS NEED
 TO BE REVISED ON THE INSTALLATION
 SCHEDULE. SEE THE ENGINEERED DRAWINGS
 FOR MINIMUM SPACING REQUIRED ON WOOD
 CONSTRUCTION.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2003-06-27 Cont ID  
Sent By shernand Date 2003-07-02 Time 11:37 Rev Time 2.00
Received By jgomez Date 2003-06-27 Time 09:47 Sent To PC
Notes
2003-06-27 00:00:00BUILDING REVIEW APPROVED WITH PROVISO:
 1-REVISE FRONT EXTERIOR ELEVATION TO
 SHOW HORIZONTAL SLIDER WINDOWS AS
 SPECIFIED ON WINDOW SCHEDULE.
 2-REVISE TRUSS ANCHOR SCHEDULE AND ALL
 DETAILS THAT ARE AFFECTED BY SECTION
 1609.4.3 FBC 2001, WHICH DOESN'T
 ALLOW THE STEEL ALLOWABLE STRESS TO BE
 USED.
 3-STORM SHUTTERS: REVISE ANCHOR SPACING
 FOR WOOD ANCHORS SHOWN ON THE INSTA-
 LLATION SCHEDULE. SEE THE ENGINEERED
 DRAWINGS FOR PROPER SPACING.

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2003-11-07 Cont ID  
Sent By btrobaug Date 2003-11-07 Time 16:50 Rev Time 0.33
Received By btrobaug Date 2003-11-07 Time 16:46 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2003-06-10 Cont ID  
Sent By csiegber Date 2003-10-24 Time 09:36 Rev Time 0.50
Received By btrobaug Date 2003-06-10 Time 13:25 Sent To P
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2003-11-03 Cont ID  
Sent By csiegber Date 2003-11-03 Time 14:33 Rev Time 0.00
Received By csiegber Date 2003-11-03 Time 14:33 Sent To M
Notes
2003-11-03 00:00:00TO PK BOX/REV

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2003-10-24 Cont ID  
Sent By csiegber Date 2003-10-24 Time 09:36 Rev Time 0.00
Received By csiegber Date 2003-10-24 Time 09:36 Sent To E
Notes
2003-10-24 00:00:00TO BT DESK/REV

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-07-02 Cont ID  
Sent By shernand Date 2003-07-02 Time 11:37 Rev Time 0.00
Received By shernand Date 2003-07-02 Time 11:37 Sent To B
Notes
2003-07-02 00:00:00JGOMEZ DESK

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-05-28 Cont ID  
Sent By shernand Date 2003-05-28 Time 09:29 Rev Time 0.00
Received By shernand Date 2003-05-28 Time 09:29 Sent To Z
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2003-11-13 Cont ID  
Sent By pkrauss Date 2003-11-13 Time 15:23 Rev Time 0.25
Received By pkrauss Date 2003-11-13 Time 15:22 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2003-06-23 Cont ID  
Sent By csiegber Date 2003-11-03 Time 14:33 Rev Time 0.25
Received By pkrauss Date 2003-06-23 Time 06:49 Sent To B
Notes
2003-06-23 00:00:00MECHANICAL PERMIT 03052035

Review Stop P PLUMBING
Rev No 1 Status P Date 2003-06-21 Cont ID  
Sent By btrobaug Date 2003-06-10 Time 13:33 Rev Time 0.25
Received By jleech Date 2003-06-21 Time 08:23 Sent To M
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2003-05-28 Cont ID  
Sent By shernand Date 2003-05-28 Time 09:29 Rev Time 1.00
Received By mmclean Date   Time   Sent To E
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved