| Plan Review Stops For Permit 03030866 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
4 |
Status |
P |
Date |
2003-07-08 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2003-07-08 |
Time |
11:11 |
Rev Time |
0.33 |
| Received By |
jgomez |
Date |
2003-07-08 |
Time |
11:10 |
Sent To |
PC |
|
| Notes |
| 2003-07-08 00:00:00 | UPDATED TRUSS ANCHOR SCHEDULE. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2003-06-17 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2003-06-17 |
Time |
08:52 |
Rev Time |
0.50 |
| Received By |
jgomez |
Date |
2003-06-17 |
Time |
08:52 |
Sent To |
|
|
| Notes |
| 2003-06-17 00:00:00 | STORM SHUTTERS PROVISO: | | | A)PANELS FOR OPENING #7 NEED TO BE | | | INCREASED IN LENGTH AS REQUIRED ON | | | ENGINEERED DRAWINGS MIN. PANEL SPAN. | | | B)ANCHORS NEED TO BE SPACED 12"O.C. MAX. | | | (NOT 12.5") IF EDGE DISTANCE IS 2". | | | SEE ENGINEERED DRAWINGS. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2003-05-29 |
|
|
Cont ID |
|
| Sent By |
shernand |
Date |
2003-06-11 |
Time |
15:26 |
Rev Time |
2.00 |
| Received By |
jgomez |
Date |
2003-05-28 |
Time |
11:46 |
Sent To |
|
|
| Notes |
| 2003-05-28 00:00:00 | BUILDING REVIEW APPROVED WITH PROVISO: | | | 1-UPDATE TRUSS ANCHOR SCHEDULE AND ALL | | | DETAILS/SPECS THAT ARE AFFECTED BY | | | SEC. 1609.4.3 FBC 2001, WHICH DOESN'T | | | ALLOW THE 33% ALLOWABLE STRESS TO BE | | | USED. SEE USP 2003 CATALOGUE FOR | | | REVISED VALUES. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2003-04-10 |
|
|
Cont ID |
|
| Sent By |
shernand |
Date |
2003-05-23 |
Time |
14:56 |
Rev Time |
2.00 |
| Received By |
jgomez |
Date |
2003-04-10 |
Time |
09:27 |
Sent To |
|
|
| Notes |
| 2003-04-10 00:00:00 | BUILDING REVIEW CHECKLIST: | | | 1-EXTERIOR REAR ELEVATION EXCEEDS THE | | | MAXIMUM OPENINGS ALLOWED BY TABLE 600 | | | FBC 2001. REVISE AS REQUIRED. | | | 2-RE-SUBMIT ENERGY CALCULATIONS WITH | | | ENGINEER'S ORIGINAL SIGNATURE AND SEAL | | | AS REQUIRED BY CHAPTER 471 FLORIDA | | | STATUTES AND SECTION 103.0 CHAPTER 13 | | | FBC 2001. | | | 3-RE-SUBMIT STORM PANELS INFORMATION W/ | | | UPDATED SBCCI PRODUCT APPROVAL THAT | | | MATCHES ENGINEERED DRAWINGS. ALSO, | | | REVISE INSTALLATION SCHEDULE SHOWING | | | CORRECT DESIGN PRESSURES AND MAX/MIN. | | | PANEL SPANS AS SHOWN ON ENGINEERED | | | DRAWINGS.SECTION 104.2.1.2 CITY | | | AMENDMENTS TO FBC 2001. | | | 4-REVISE DETAIL S-26. IT DOESN'T APPLY. | | | SEE 2ND FL. FRAMING PLAN AND PROVIDE | | | COMPLETE DETAIL SHOWING ACTUAL FRAMING | | | CONDITIONS AND CONNECTOR FOR COLUMN | | | LOCATED BETWEEN GARAGE AND KITCHEN. | | | SEC. 104.2.1.2 CITY AMENDMENTS TO FBC. |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
3 |
Status |
P |
Date |
2003-10-31 |
|
|
Cont ID |
|
| Sent By |
btrobaug |
Date |
2003-10-31 |
Time |
15:35 |
Rev Time |
0.50 |
| Received By |
btrobaug |
Date |
2003-10-31 |
Time |
15:31 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
P |
Date |
2003-09-29 |
|
|
Cont ID |
|
| Sent By |
btrobaug |
Date |
2003-09-29 |
Time |
13:27 |
Rev Time |
0.33 |
| Received By |
btrobaug |
Date |
2003-09-29 |
Time |
13:27 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2003-04-03 |
|
|
Cont ID |
|
| Sent By |
csiegber |
Date |
2003-09-17 |
Time |
16:21 |
Rev Time |
0.25 |
| Received By |
dpalmer |
Date |
2003-04-03 |
Time |
17:06 |
Sent To |
P |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2003-09-17 |
|
|
Cont ID |
|
| Sent By |
csiegber |
Date |
2003-09-17 |
Time |
16:21 |
Rev Time |
0.00 |
| Received By |
csiegber |
Date |
2003-09-17 |
Time |
16:21 |
Sent To |
E |
|
| Notes |
| 2003-09-17 00:00:00 | TO BT DESK |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2003-06-11 |
|
|
Cont ID |
|
| Sent By |
shernand |
Date |
2003-06-11 |
Time |
15:26 |
Rev Time |
0.00 |
| Received By |
shernand |
Date |
2003-06-11 |
Time |
15:26 |
Sent To |
B |
|
| Notes |
| 2003-06-11 00:00:00 | JGOMEZ DESK |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2003-05-23 |
|
|
Cont ID |
|
| Sent By |
shernand |
Date |
2003-05-23 |
Time |
14:56 |
Rev Time |
0.00 |
| Received By |
shernand |
Date |
2003-05-23 |
Time |
14:56 |
Sent To |
B |
|
| Notes |
| 2003-05-23 00:00:00 | JGOMEZ DESK |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2003-03-12 |
|
|
Cont ID |
|
| Sent By |
sthyng |
Date |
2003-03-12 |
Time |
14:24 |
Rev Time |
0.00 |
| Received By |
sthyng |
Date |
2003-03-12 |
Time |
14:24 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
P |
Date |
2003-04-07 |
|
|
Cont ID |
|
| Sent By |
hmoser |
Date |
2003-04-07 |
Time |
18:34 |
Rev Time |
0.25 |
| Received By |
hmoser |
Date |
2003-04-07 |
Time |
18:34 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
P |
Date |
2003-04-01 |
|
|
Cont ID |
|
| Sent By |
jleech |
Date |
2003-04-03 |
Time |
19:09 |
Rev Time |
0.35 |
| Received By |
pkrauss |
Date |
2003-04-01 |
Time |
13:26 |
Sent To |
E |
|
| Notes |
| 2003-04-01 00:00:00 | MECHANICAL PERMIT 03030899 |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2003-04-03 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-04-03 |
Time |
17:06 |
Rev Time |
0.33 |
| Received By |
jleech |
Date |
2003-04-03 |
Time |
19:09 |
Sent To |
M |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2003-05-28 |
|
|
Cont ID |
|
| Sent By |
sthyng |
Date |
2003-03-12 |
Time |
14:24 |
Rev Time |
1.00 |
| Received By |
mmclean |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|