Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2003-04-02 Cont ID  
Sent By shernand Date 2003-05-05 Time 15:03 Rev Time 2.50
Received By lhatten Date 2003-03-30 Time 06:18 Sent To  
Notes
2003-04-02 00:00:00REVIEW & PRINT CARD 03/30/2003

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2003-04-09 Cont ID  
Sent By btrobaug Date 2003-04-09 Time 07:15 Rev Time 1.00
Received By btrobaug Date 2003-04-09 Time 06:44 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2003-03-17 Cont ID  
Sent By shernand Date 2003-04-04 Time 14:18 Rev Time 0.75
Received By btrobaug Date 2003-03-17 Time 14:24 Sent To P
Notes
2003-03-17 00:00:00UNSAT
 ~~~~~
 ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
 PLEASE PROVIDE THE FOLLOWING
 INFORMATIONAND RESUBMIT FOR REVIEW.
  
 1} THE GEC IS INCORRECT FOR 300 AMP.
 SERVICE,SEE 250-66.
  
 2} HOW IS THE 2ND DISCONNECT BEING FED?
 PLANS SHOW A CONDUIT TO ONE WITH 6
 WIRES, PLEASE CLARIFY.
  
 3} A LAUNDRY CIRCUIT MUST BE CALCULATED
 PER 220-16(B).
  
 4} PLEASE LIST THE REQ'D ARC
 FAULT PROTECTED CIRCUITS ON PANEL
 SCHEDULE OR NOTE ON PLANS FOR BRANCH
 CIRCUIT PROTECTION. PER 210-12
  
 5} PLEASE SHOW GARAGE RECEPTACLES TO
 COMPLY WITH 210-8.
  
 IF THERE ARE ANY QUESTIONS PLEASE CALL.
  
 BILL TROBAUGH
 ELECTRICAL PLAN REVIEW
 561/659-8096 EXT.8392

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2003-05-20 Cont ID  
Sent By shernand Date 2003-05-20 Time 16:41 Rev Time 0.00
Received By shernand Date 2003-05-20 Time 16:41 Sent To P
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2003-05-05 Cont ID  
Sent By shernand Date 2003-05-05 Time 15:02 Rev Time 0.00
Received By shernand Date 2003-05-05 Time 15:02 Sent To B
Notes
2003-05-05 00:00:00LHATTEN DESK, REVISION.

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2003-04-04 Cont ID  
Sent By shernand Date 2003-04-04 Time 14:18 Rev Time 0.00
Received By shernand Date 2003-04-04 Time 14:18 Sent To E
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-03-04 Cont ID  
Sent By dpalmer Date 2003-03-04 Time 08:31 Rev Time 0.00
Received By dpalmer Date 2003-03-04 Time 08:31 Sent To Z
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-02-27 Cont ID  
Sent By dpalmer Date 2003-02-27 Time 13:52 Rev Time 0.00
Received By dpalmer Date 2003-02-27 Time 13:52 Sent To Z
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2003-03-19 Cont ID  
Sent By jleech Date 2003-03-17 Time 19:02 Rev Time 0.50
Received By hmoser Date 2003-03-19 Time 17:16 Sent To B
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2003-05-24 Cont ID  
Sent By kstevens Date 2003-05-24 Time 17:03 Rev Time 0.50
Received By kstevens Date 2003-05-24 Time 17:03 Sent To  
Notes
2003-05-24 00:00:00REVISION OK - SANT. RISER DIAGRAM

Review Stop P PLUMBING
Rev No 1 Status P Date 2003-03-17 Cont ID  
Sent By shernand Date 2003-05-20 Time 16:41 Rev Time 0.33
Received By jleech Date 2003-03-17 Time 19:01 Sent To M
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2003-03-04 Cont ID  
Sent By dpalmer Date 2003-03-04 Time 08:31 Rev Time 0.00
Received By sgraham Date   Time   Sent To P
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved