| Plan Review Stops For Permit 03011384 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
4 |
Status |
P |
Date |
2003-03-19 |
|
|
Cont ID |
|
| Sent By |
hpiskura |
Date |
2003-03-19 |
Time |
07:27 |
Rev Time |
0.00 |
| Received By |
hpiskura |
Date |
2003-03-19 |
Time |
07:27 |
Sent To |
|
|
| Notes |
| 2003-03-19 00:00:00 | REVISIONS DATED 2/7/03 AND 2/12/03. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2003-03-05 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-03-17 |
Time |
06:36 |
Rev Time |
0.00 |
| Received By |
hpiskura |
Date |
2003-03-05 |
Time |
07:08 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2003-02-27 |
|
|
Cont ID |
|
| Sent By |
btrobaug |
Date |
2003-02-28 |
Time |
17:09 |
Rev Time |
0.00 |
| Received By |
hpiskura |
Date |
2003-02-26 |
Time |
16:13 |
Sent To |
|
|
| Notes |
| 2003-02-26 00:00:00 | THE ALBERT A. GARGIULO, PE PLAN S1 | | | DATED2/17/03 DOES NOT HAVE SUFFICIENT | | | FOUNDATION INFORMATION. | | | | | | SECTION 1 CALLS FOR A 3000# CAPACITY | | | TIEDOWN.NOTE 1 CALLS FOR 6200# MIN | | | ULTIMATE. | | | | | | THE SCHEDULE SHOWS THREE PIER TYPES. | | | NONE ARE SELECTED.THE PLANS DO NOT | | | SHOW THE LOCATION, PLACEMENT, TYPE OR | | | NUMBER OF PIERS TO BE USED. | | | | | | THE SCHEDULE SHOWS TWO SOIL BEARING | | | VALUES AS A FUNCTION OF VERTICAL TIES | | | TO BE INCORPORATED.NO SELECTION IS | | | SHOWN. | | | | | | THE FOUNDATION ENGINEER SHOULD REVIEW | | | THE NOTE UNDER "FOUNDATION" ON SHEET OF | | | 1 OF 3 OF THE IMS PLAN DATED 11/12/02 | | | AND CHAPTER 61G15-31 RESPONSIBILTY | | | RULES FO PROFESSIONAL ENGINEER | | | CONCERNING THE DESIGN OF STRUCTURES, OF | | | THE FLORIDA ADMINISTRATIVE CODE. | | | | | | THE FOUNDATION NOTES ARE NOT VERY | | | LEGIBLE. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2003-02-05 |
|
|
Cont ID |
|
| Sent By |
hpiskura |
Date |
2003-02-05 |
Time |
15:29 |
Rev Time |
0.00 |
| Received By |
hpiskura |
Date |
2003-02-05 |
Time |
15:28 |
Sent To |
|
|
| Notes |
| 2003-02-05 00:00:00 | PLEASE PROVIDE A FOUNDATION PLAN FOR THE | | | RELOCATED MODULAR BUILDING. |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
4 |
Status |
P |
Date |
2003-03-17 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-03-17 |
Time |
06:36 |
Rev Time |
0.25 |
| Received By |
dpalmer |
Date |
2003-03-17 |
Time |
06:36 |
Sent To |
B |
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
3 |
Status |
P |
Date |
2003-02-25 |
|
|
Cont ID |
|
| Sent By |
lmartine |
Date |
2003-03-13 |
Time |
18:14 |
Rev Time |
0.25 |
| Received By |
dpalmer |
Date |
2003-02-25 |
Time |
13:28 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
F |
Date |
2003-02-20 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-02-20 |
Time |
18:55 |
Rev Time |
0.25 |
| Received By |
dpalmer |
Date |
2003-02-20 |
Time |
18:55 |
Sent To |
|
|
| Notes |
| 2003-02-20 00:00:00 | ************* UNSAT ************** | | | | | | 1)NOTE: PLEASE SEE PLANS, PLANS HAVE | | | A HANDWRITTEN NOTE THAT MENTIONS,PANEL | | | TO BE REMOVED?? PLEASE CLARIFY HOW | | | UNIT/BLDG IS GOING TO BE FED IF PANEL | | | IS REMOVED? PLEASE ALSO NOTE, PER FS/FAC | | | ALL CHANGES TO PLANS MUST BE DONE BY THE | | | ARCH/ ENGINEER OF RECORD. 471.025/, | | | 481.221 | | | | | | PLEASE SEE FIRST REVIEW NOTES AND SUBMIT | | | THE ABOVE INFORMATION FOR REVIEW. IF | | | THERE ARE ANY QUESTIONS,PLEASE CALL. | | | | | | DEWEY PALMER | | | ELECTRICAL PLAN REVIEW | | | 561-659-8096 EXT 8372 |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
F |
Date |
2003-01-28 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-01-28 |
Time |
06:12 |
Rev Time |
0.33 |
| Received By |
dpalmer |
Date |
2003-01-28 |
Time |
06:10 |
Sent To |
|
|
| Notes |
| 2003-01-28 00:00:00 | **********UNSAT ****************** | | | | | | 1)NOTE: PLEASE NOTE, PANEL IS SHOWN | | | BEHIND DESK AREA ON PLAN. IT IS NOTED | | | THAT "DESK IS MOVABLE" . PLEASE NOTE | | | PER NEC 110-26 WORKING CLEARENCES ARE | | | ALL THE TIME. PLEASE ADJUST FURNITURE | | | LAYOUT TO MEET 110-26. | | | | | | PLEASE SUBMIT THE ABOVE INFORMATION FOR | | | REVIEW. IF THERE ARE ANY QUESTIONS, | | | PLEASE CALL. | | | | | | DEWEY PALMER | | | ELECTRICAL PLAN REVIEW | | | 561-659-8096 EXT 8372 | | | | | | 2)NOTE: PLEASE SUBMIT/SHOW AIC RATING | | | FOR NEW MAIN DISCONNECT. 110-9 |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2003-02-10 |
|
|
Cont ID |
|
| Sent By |
nmccray |
Date |
2003-02-10 |
Time |
11:12 |
Rev Time |
0.00 |
| Received By |
nmccray |
Date |
2003-02-10 |
Time |
11:12 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
6 |
Status |
|
Date |
2003-03-13 |
|
|
Cont ID |
|
| Sent By |
lmartine |
Date |
2003-03-13 |
Time |
18:14 |
Rev Time |
0.00 |
| Received By |
lmartine |
Date |
|
Time |
|
Sent To |
E |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
5 |
Status |
N |
Date |
2003-03-06 |
|
|
Cont ID |
|
| Sent By |
sgraham |
Date |
2003-03-13 |
Time |
09:47 |
Rev Time |
0.00 |
| Received By |
dpalmer |
Date |
2003-03-06 |
Time |
14:23 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2003-02-28 |
|
|
Cont ID |
|
| Sent By |
btrobaug |
Date |
2003-02-28 |
Time |
17:09 |
Rev Time |
0.00 |
| Received By |
btrobaug |
Date |
2003-02-28 |
Time |
17:09 |
Sent To |
B |
|
| Notes |
| 2003-02-28 00:00:00 | TO HHP./WRT |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2003-02-20 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-02-20 |
Time |
09:14 |
Rev Time |
0.00 |
| Received By |
dpalmer |
Date |
2003-02-20 |
Time |
09:14 |
Sent To |
|
|
| Notes |
| 2003-02-20 00:00:00 | TO COMM BOARD #21 |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2003-01-27 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-01-27 |
Time |
06:11 |
Rev Time |
0.00 |
| Received By |
dpalmer |
Date |
2003-01-27 |
Time |
06:11 |
Sent To |
|
|
| Notes |
| 2003-01-28 00:00:00 | TO COMM BOARD #9 |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2003-01-23 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-01-23 |
Time |
09:27 |
Rev Time |
0.00 |
| Received By |
dpalmer |
Date |
2003-01-23 |
Time |
09:27 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
N |
Date |
2003-03-05 |
|
|
Cont ID |
|
| Sent By |
sgraham |
Date |
2003-01-24 |
Time |
16:04 |
Rev Time |
0.00 |
| Received By |
hpiskura |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2003-03-13 |
|
|
Cont ID |
|
| Sent By |
sgraham |
Date |
2003-03-13 |
Time |
09:46 |
Rev Time |
0.00 |
| Received By |
sgraham |
Date |
|
Time |
|
Sent To |
I |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2003-01-24 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-03-06 |
Time |
14:23 |
Rev Time |
0.00 |
| Received By |
sgraham |
Date |
|
Time |
|
Sent To |
P |
|
| Notes |
|
|