| Plan Review Stops For Permit 02120313 |
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
P |
Date |
2003-04-21 |
|
|
Cont ID |
|
| Sent By |
btrobaug |
Date |
2003-04-21 |
Time |
17:29 |
Rev Time |
0.50 |
| Received By |
btrobaug |
Date |
2003-04-21 |
Time |
17:29 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2002-12-31 |
|
|
Cont ID |
|
| Sent By |
shernand |
Date |
2003-04-18 |
Time |
16:49 |
Rev Time |
0.50 |
| Received By |
btrobaug |
Date |
2002-12-31 |
Time |
11:41 |
Sent To |
M |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2003-04-18 |
|
|
Cont ID |
|
| Sent By |
shernand |
Date |
2003-04-18 |
Time |
16:49 |
Rev Time |
0.00 |
| Received By |
shernand |
Date |
2003-04-18 |
Time |
16:49 |
Sent To |
E |
|
| Notes |
| 2003-04-18 00:00:00 | BT DESK |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2003-01-24 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2003-01-24 |
Time |
12:13 |
Rev Time |
0.00 |
| Received By |
dpalmer |
Date |
2003-01-24 |
Time |
12:13 |
Sent To |
B |
|
| Notes |
| 2003-01-24 00:00:00 | TO ROBERT MCDOUGALS DESK. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2002-12-19 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2002-12-19 |
Time |
10:38 |
Rev Time |
0.00 |
| Received By |
dpalmer |
Date |
2002-12-19 |
Time |
10:38 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2002-12-09 |
|
|
Cont ID |
|
| Sent By |
btrobaug |
Date |
2002-12-09 |
Time |
13:18 |
Rev Time |
0.00 |
| Received By |
btrobaug |
Date |
2002-12-04 |
Time |
13:18 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
N |
Date |
2003-01-04 |
|
|
Cont ID |
|
| Sent By |
btrobaug |
Date |
2002-12-31 |
Time |
12:19 |
Rev Time |
0.50 |
| Received By |
hmoser |
Date |
2003-01-04 |
Time |
09:49 |
Sent To |
R |
|
| Notes |
| 2003-01-04 00:00:00 | PASS/PROVISO | | | 1) NEED HVAC.EFFICIENCY CARD POSTED ON | | | A/C EQUIPMENT FOR FINAL | | | 2) NEED A/C EQUIPMENT SPECIFICATIONS | | | FOR FINAL | | | PLAN REVIEW BY HAROLD MOSER | | | (561)659-8096 EXT.8221 |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2002-12-28 |
|
|
Cont ID |
|
| Sent By |
sgraham |
Date |
2002-12-23 |
Time |
12:48 |
Rev Time |
0.33 |
| Received By |
jleech |
Date |
2002-12-28 |
Time |
13:01 |
Sent To |
M |
|
| Notes |
|
|
| Review Stop |
R |
ROOF PLAN REVIEW |
| Rev No |
2 |
Status |
P |
Date |
2003-01-30 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2003-01-30 |
Time |
10:52 |
Rev Time |
3.00 |
| Received By |
rmcdouga |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2003-01-30 00:00:00 | BUILDING PROVISO | | | | | | 1) PROVIDE A CORRECTED STORM PANEL | | | INSTALLATION SCHEDULE. | | | | | | 2)PROVIDE (2) CURRENT AND COMPLETE | | | COPIES OF SBCCI OR METRO-DADE PRODUCT | | | APPROVALS FOR THE FOLLOWING PRIOR TO | | | INSTALLING. | | | - (FRONT DOOR) SINGLE OUTSWING DOOR WITH | | | ONE SIDELITE | | | - ARCHED TOP WINDOW (BEDROOM #2) |
|
|
| Review Stop |
R |
ROOF PLAN REVIEW |
| Rev No |
1 |
Status |
F |
Date |
2003-01-10 |
|
|
Cont ID |
|
| Sent By |
hmoser |
Date |
2003-01-04 |
Time |
09:49 |
Rev Time |
4.00 |
| Received By |
rmcdouga |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2003-01-08 00:00:00 | BUILDING DENIED | | | | | | 1) A RECORDED COPY OF THE NOTICE OF | | | COMMENCEMENT MUST BE SUBMITTED BEFORE A | | | PERMIT CAN BE ISSUED. | | | | | | 2) THE ENERGY CALCULATION FORM IS | | | REQUIRED TO BE SIGNED BY THE OWNER/AGENT | | | | | | 3) THE UPLIFTS GIVEN ON THE ROOF FRAMING | | | PLAN ON S2, EXCEED THE CAPACITIES OF THE | | | SPECIFIED CONNECTORS AT SEVERAL | | | LOCATIONS. SEE REDLINES ON PLANS. | | | | | | 4) CLARIFY THE CONNECTOR AND THE UPLIFT | | | FOR THE HIP GIRDER OVER THE GARAGE. THE | | | OUTER END HAS 1588# OF UPLIFT AND B ON | | | S2 CONNECTOR IS SPECIFIED. THE CONNECTOR | | | OON THE OTHER END (ENTRY) IS A USP MSH | | | WHICH HAS A UPLIFT CAPACITY OF 785#. | | | PLEASE REVIEW. | | | | | | 5) THE ROOF NAILING ZONE FOR THE GABLE | | | END OVER BEDROOM #2 IS ZONE 3 FOR 4' | | | FROM GABLE PLUS OVERHANG. PLEASE CORRECT | | | THE DIAGRAM ON S2. | | | | | | 6) ACCORDING TO THE STORM PANEL KEY PLAN | | | UNITS 1 & 2 ON THE INSTALLATION SCHEDULE | | | ARE REVERSED. UNIT 6 (2) SH 25 WITH 24" | | | TRANSOM ABOVE HAS THE WRONG OPENING SIZE | | | LISTED ON THE SCHEDULE. THE OPENING SIZE | | | FOR UNIT 8 IS ALSO INCORRECT. | | | | | | 7)PROVIDE (2) CURRENT AND COMPLETE | | | COPIES OF SBCCI OR METRO-DADE PRODUCT | | | APPROVALS FOR: | | | - SLIDING GLASS DOORS | | | - SINGLE OUTSWING DOOR WITH ONE SIDELITE | | | - ARCHED TOP WINDOW (BEDROOM #2) | | | | | | 8) PROVIDE A SOIL BEARING TEST REPORT AS | | | REQUIRED BY FBC 1804.2.2. | | | | | | ROBERT MCDOUGAL | | | BLDG. PLAN REVIEW | | | (561)659-8096 EXT.8202 | | | | | | 659-8096 EXT.8202 |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2002-12-23 |
|
|
Cont ID |
|
| Sent By |
sgraham |
Date |
2002-12-23 |
Time |
12:48 |
Rev Time |
0.25 |
| Received By |
sgraham |
Date |
|
Time |
|
Sent To |
P |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2002-12-12 |
|
|
Cont ID |
|
| Sent By |
dpalmer |
Date |
2002-12-19 |
Time |
10:38 |
Rev Time |
0.25 |
| Received By |
sgraham |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2002-12-12 00:00:00 | DENIED, NEED SITE PLAN |
|
|