Plan Review Details - Permit 02100049
Plan Review Stops For Permit 02100049
Review Stop E ELECTRICAL
Rev No 2 Status P Date 2003-01-06 Cont ID  
Sent By dpalmer Date 2003-01-06 Time 19:43 Rev Time 0.50
Received By dpalmer Date 2003-01-06 Time 19:02 Sent To P
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2002-10-22 Cont ID  
Sent By dpalmer Date 2003-01-06 Time 18:57 Rev Time 0.50
Received By dpalmer Date 2002-10-22 Time 10:21 Sent To B
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2003-04-01 Cont ID  
Sent By sthyng Date 2003-04-01 Time 10:29 Rev Time 0.00
Received By sthyng Date 2003-04-01 Time 10:28 Sent To M
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2003-02-06 Cont ID  
Sent By dpalmer Date 2003-02-06 Time 16:25 Rev Time 0.00
Received By dpalmer Date 2003-02-06 Time 16:25 Sent To B
Notes
2003-02-06 00:00:00TO ROBERT MC DOUGALS DESK.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2003-01-06 Cont ID  
Sent By dpalmer Date 2003-01-06 Time 18:57 Rev Time 0.00
Received By dpalmer Date 2003-01-06 Time 18:57 Sent To E
Notes
2003-01-06 00:00:00TO ELEC IN BOX FOR RESTAMP.

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2003-04-04 Cont ID  
Sent By pkrauss Date 2003-04-04 Time 13:14 Rev Time 0.30
Received By pkrauss Date 2003-04-04 Time 11:45 Sent To  
Notes
2003-04-04 00:00:00MECH REV PERMIT 02100120

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2002-10-19 Cont ID  
Sent By sthyng Date 2003-04-01 Time 10:29 Rev Time 0.33
Received By jleech Date 2002-10-19 Time 13:09 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2003-01-13 Cont ID  
Sent By kstevens Date 2003-01-13 Time 18:18 Rev Time 0.25
Received By kstevens Date 2003-01-13 Time 18:18 Sent To R
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2002-10-19 Cont ID  
Sent By dpalmer Date 2003-01-06 Time 19:44 Rev Time 0.25
Received By jleech Date 2002-10-19 Time 13:09 Sent To  
Notes
***NONE***

Review Stop R ROOF PLAN REVIEW
Rev No 3 Status P Date 2003-02-10 Cont ID  
Sent By rmcdouga Date 2003-02-10 Time 15:40 Rev Time 4.00
Received By rmcdouga Date   Time   Sent To  
Notes
2003-02-10 00:00:00BUILDING PROVISO
  
 SUBMIT A SOIL TEST REPORT AND SOIL
 DENSITY REPORT PRIOR TO POURING THE
 FOUNDATION, PER L. HATTEN.

Review Stop R ROOF PLAN REVIEW
Rev No 2 Status F Date 2003-01-15 Cont ID  
Sent By kstevens Date 2003-01-13 Time 18:18 Rev Time 4.00
Received By rmcdouga Date   Time   Sent To  
Notes
2003-01-15 00:00:00BUILDING DENIED
  
 1) IMPACT FEES MUST BE PAID TO PALM
 BEACH COUNTY, PLANS STAMPED BY THEM AND
 COPY OF RECEIPT SUBMITTED TO CITY OF
 WEST PALM BEACH BUILDING DEPARTMENT,
 BEFORE A BUILDING PERMIT CAN BE ISSUED.
  
 2) A RECORDED COPY OF THE NOTICE OF
 COMMENCEMENT MUST BE SUBMITTED BEFORE A
 PERMIT CAN BE ISSUED.
  
 3) PROVIDE A SOIL TEST REPORT PRIOR TO
 POURING THE FOUNDATION PER L.HATTEN.
  
 4) THE SURVEY SUBMITTED DOES NOT MATCH
 THE FOOTPRINT OF THE STRUCTURE SHOWN ON
 THE PLANS. THE STRUCTURES FOOTPRINT ON
 THE LANDSCAPE PLAN DOES NOT CORRESPOND
 WITH THE REST OF THE PLANS. THE COVERED
 ENTRY AND COVERED PATIOS DIFFER. PLEASE
 CORRECT.
  
 5) PLEASE REVISE THE FASTENING
 REQUIREMENTS FOR THE HORIZONTAL WIRE
 LATH ON A2. ASTM C 1063 REQUIRES THE
 FASTENERS TO PENETRATE 1-3/4" INTO
 HORIZONTAL WOOD FRAMING MEMBERS. THE
 FASTENER SPACING FOR 3/8" RIB LATH IS
 AT EVERY RIB (4"O.C.)
  
 6) THE 50"X60" FIXED GLASS WINDOW
 BETWEEN THE 25SH WINDOWS AT THE MASTER
 BEDROOM REQUIRES A DESIGN WINDLOAD OF
 +47.4 AND - 59.9 PSF. THE PRODUCT
 APPROVAL SUBMITTED HAS A + OR - 42.6 PSF
 DESIGN WINDLOAD FOR THIS SIZE WINDOW,
 WHICH DOES NOT MEET THE REQUIRED LOADS.
  
 D) THE PRODUCT APPROVAL FOR THE FOUR
 PANEL SLIDING GLASS DOOR DOES NOT MEET
 THE REQUIRED WINDLOAD PRESSURES LISTED
 ON THE PLANS.
  
 8) THE SITE SPECIFIC PRODUCT APPROVAL
 FOR THE DOUBLE OUTSWING DOORS IS
 REQUIRED TO BE SIGNED, SEALED AND DATED
 BY THE DESIGNER OF RECORD FOR THE
 STRUCTURE.
  
 9) SPECIFY THE EMBEDMENT DEPTH OF THE
 3/4" DIAMETER WEDGE ANCHORS SPECIFIED
 FOR THE USC AND NFM CONNECTORS ON A8.
  
 10) SAFETY GLASS IS REQUIRED IN THE
 WINDOW AT THE TUB IN BATH #2 AND IN THE
 WINDOW AT THE SHOWER IN THE MASTER BATH.
 PLEASE NOTE ON PLANS.
  
 ROBERT MCDOUGAL
 BLDG. PLAN REVIEW
 (561)659-8096 EXT.8202

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status F Date 2002-10-30 Cont ID  
Sent By rmcdouga Date 2002-10-30 Time 14:41 Rev Time 6.00
Received By rmcdouga Date   Time   Sent To  
Notes
2002-10-30 00:00:00BUILDING DENIED
  
 1) IMPACT FEES MUST BE PAID TO PALM
 BEACH COUNTY, PLANS STAMPED BY THEM AND
 COPY OF RECEIPT SUBMITTED TO CITY OF
 WEST PALM BEACH BUILDING DEPARTMENT,
 BEFORE A BUILDING PERMIT CAN BE ISSUED.
  
 2) A RECORDED COPY OF THE NOTICE OF
 COMMENCEMENT MUST BE SUBMITTED BEFORE A
 PERMIT CAN BE ISSUED.
  
 3) PROVIDE COMPLETE SOIL TEST REPORT
 SIGNED AND SEALED BY SOIL ENGINEER.
  
 4) INDICATE ON THE PLANS THE DRAFTSTOP
 LOCATIONS AND MATERIALS FOR THE FLOOR/
 CEILING ASSEMBLY REQUIRED BY 2001 FBC
 SEC. 2305.2.2.
  
 5) REVISE OPENING SIZE OF SECOND FLOOR
 ATTIC ACCESS TO COMPLY WITH FBC 2309.6.
  
 6) PROVIDE CALCULATIONS WHICH INDICATE
 THAT THE REQUIRED NET FREE VENTILATING
 AREA WILL BE PROVIDED BY AREAS WITHOUT
 STYROFOAM TRIM. SEE FBC 2309.7.1.
  
 7) PROVIDE A STRUCTURAL PLAN FOR THE
 STAIRS INDICATING HOW STAIRS AND LANDING
 WILL BE SUPPORTED.
  
 8) PROVIDE A STAIR SECTION INDICATING
 THE LOCATION AND MATERIALS USED FOR
 FIREBLOCKING. FBC 2305.1.4.
  
 9) REVISE WOOD STAIR DETAIL ON A12 FOR
 HANDRAIL GRASPABILITY. SEE FBC 1007.5.3
 DO NOT SITE CODE SECTIONS. PROVIDE
 SPECIFIC INFORMATION AS REQUIRED BY FBC
 104.2.1.
  
 10)SPECIFY ONE HOUR RATED GLASS BLOCK AT
 ZERO LOT LINE. REVISE GLASS BLOCK DETAIL
 ON A12 TO ONE HOUR RATED INSTALLATION.
  
 11) SPECIFY THE SIZE OF THE WASHERS FOR
 THE TAPCONS FOR THE GARAGE DOOR BUCK ON
 A12.
  
 12) SPECIFY SUPPORTS AND SPACING FOR THE
 WWM IN THE CONCRETE SLAB. FBC 1909.3
  
 13) PROVIDE STRUCTURAL DETAIL FOR THE
 BOLLARD OR 3" STEEL POST AT GARAGE.
  
 14) PROVIDE A LINTEL SCHEDULE FOR THE
 PRECAST LINTEL BETWEEN THE FRONT DOOR
 AND TRANSOM AND ABOVE WINDOWS.
  
 15) THE VENT OPENINGS IN THE GARAGE WALL
 ARE NOT ALLOWED IN A WALL ON A ZERO LOT
 LINE. PLEASE REVISE.
  
 16) THE SURVEY DOES NOT MATCH THE PLANS
 AT THE REAR COVERED PATIO. PLEASE
 REVISE.
  
 17) INDICATE THE CEILING FINISHES AT THE
 COVERED LANAI/PATIO AND ENTRY. IF WIRE
 LATH AND STUCCO, PROVIDE ATTACHMENT
 DETAILS. SEE ASTM C 926 & ASTM C 1063.
  
 18) REVISE ROOF SHEATHING NAILING
 SCHEDULE. RING SHANK 8D NAILS ARE
 REQUIRED IN ZONE 3 FOR STRUCTURES WITH A
 MEAN ROOF HEIGHT OF 25'.
  
 19) REVISE SWING DOOR BUCK DETAIL ON A12
 TO COMPLY WITH FBC 1707.4.4.2.
  
 20)PROVIDE (2) PRODUCT APPROVALS, KEY
 PLANS AND INSTALLATION SCHEDULES
 INDICATING THE SPECIFIC TYPES OF ANCHORS
 TO BE USED FOR STORM PANELS.
  
 21) BASED ON THE WINDLOAD PRESSURES IN
 THE SCHEDULE ON A1 AND THE PRODUCT
 APPROVAL SUBMITTED, FIXED GLASS WINDOWS
 U,T,H1,A1,B1,L1,F1 AND W MUST HAVE 3/16"
 TEMPERED GLASS. PLEASE SPECIFY ON THE
 PLANS.
  
 22) SAFTEY GLASS IS REQUIRED IN THE
 WINDOWS IN BATH #2 AND THE MASTER BATH
 PER FBC 2405.2. GLASS BLOCK IN MASTER
 BATH IS REQUIRED TO HAVE A MINIMUM
 UNIFORM FACE THICKNESS OF 0.25 INCH PER
 FBC 2405.2.2(5).
  
 23) THE UPLIFT VALUE GIVEN FOR THE
 DOUBLE TA CONNECTOR IS INCORRECT. REFER
 TO CURRENT USP CATALOG AND REVISE.
  
 24) THE PRODUCT APPROVAL FOR THE SGD IS
 MISSING PAGE 2 AND THE DRAWINGS DO NOT
 HAVE THE SAME NOA NUMBER AS THE APPROVAL
  
 25) SEVERAL OF THE SINGLE HUNG WINDOWS
 ON THE PLANS EXCEED THE DESIGN WINDLOADS
 IN THE PRODUCT APPROVAL.
  
 26) SPECIFY WHICH GLASS BLOCK MANUFACT-
 URER WILL BE USED AND PROVIDE LISTING
 SPECIFICATIONS FOR A ONE HOUR FIRE RATED
 ASSEMBLY.
  
 27) PROVIDE PRODUCT APPROVAL OR SITE
 SPECIFIC ENGINEERING FOR DOUBLE OUTSWING
 DOORS. USE CITY OF WPB FORM. LOCATION OF
 JOB IS REQUIRED TO BE ON FORM. FORM MUST
 BE SIGNED AND SEALED BY THE DESIGNER OF
 RECORD IN ADDITION TO THE ENGINEER.
 PROVIDE TEST REPORTS FOR IMPACT IF 1.1F
 IS CHECKED.
  
 28) PROVIDE (2) CURRENT AND COMPLETE
 COPIES OF SBCCI OR METRO-DADE PRODUCT
 APPROVALS FOR:
 - HORIZONTAL STRUCTURAL MULLIONS (THE
 ONES SUBMITTED ARE FOR VERTICAL
 APPLICATIONS ONLY
  
 ROBERT MCDOUGAL
 BLDG. PLAN REVIEW
 (561)659-8096 EXT.8202

Review Stop Z ZONING
Rev No 1 Status P Date 2002-10-15 Cont ID  
Sent By sgraham Date 2002-10-15 Time 12:28 Rev Time 0.25
Received By sgraham Date   Time   Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved