| 2002-10-01 00:00:00 | UNSAT |
| | ~~~~~ |
| | ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ |
| | |
| | PLEASE PROVIDE THE FOLLOWING |
| | INFORMATION AND MAKE NECESSARY |
| | CORRECTIONS ON PLANS. |
| | |
| | 1} PLEASE SHOW GROUNDING ELECTRODE |
| | GOING TO BUILDING STEEL AND COLD WATER |
| | PER 250-50. SIZE PER 250-66.THE NOTE ON |
| | THE GROUNDING ELECTRODE SYSTEM IN |
| | UNACCEPTABLE FOR REVIEW. PLEASE PROVIDE |
| | DETAILS OF THE GES. |
| | |
| | 2} THE LOADCENTER PANEL SCHEDULE FOR |
| | PANEL "L" INDICATES 12 SPACES,YET PANEL |
| | "L" LOAD CALCULATION INDICATES MORE |
| | LOADS NOT LISTED IN THE SCHEDULE.PLEASE |
| | CORRELATE. |
| | |
| | 3} IT IS UNCLEAR WHAT THE PURPOSE OF THE |
| | EXISTING METER FEEDING THE EXISTING 100 |
| | AMP DISCONNECT IS.IF THE NEW METER IS |
| | FEEDING THE NEW PANEL "L" WHAT IS THE |
| | EXISTING DISCONNECT FEEDING? PLEASE |
| | CLARIFY AND CORRELATE THE RISER |
| | DIAGRAM, LOAD CALCS,NUMBER & LOCATION |
| | OF PANELS,ETC. |
| | |
| | 4} ON THE RISER DIAGRAM IT APPEARS THAT |
| | THE NEW METER IS BEING FED FROM THE OLD |
| | METER,PLEASE CLARIFY.IF THERE IS ANOTHER |
| | BUILDING BEING FED FROM THIS SERVICE, |
| | SHOW GROUNDING AND DISCONNECTING MEANS |
| | AT THAT LOCATION. |
| | |
| | 5} PLEASE SUBMIT AIC RATINGS FOR |
| | ALL NEW EQUIPMENT BEING INSTALLED. |
| | MAINS/PANELS/BREAKERS MUST BE RATED FOR |
| | THE AVAILABLE FAULT CURRENT PER 110-9. |
| | |
| | |
| | IF THERE ARE ANY QUESTIONS PLEASE CALL. |
| | |
| | BILL TROBAUGH |
| | ELECTRICAL PLAN REVIEW |
| | 561/659-8096 EXT. 8392 |