Plan Review Details - Permit 02081580
Plan Review Stops For Permit 02081580
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2002-09-09 Cont ID  
Sent By hpiskura Date 2002-09-09 Time 10:48 Rev Time 0.00
Received By hpiskura Date 2002-09-09 Time 10:33 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2002-08-28 Cont ID  
Sent By dpalmer Date 2002-08-28 Time 20:29 Rev Time 0.25
Received By dpalmer Date 2002-08-28 Time 20:29 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2002-08-28 Cont ID  
Sent By mcarsill Date 2002-08-28 Time 11:33 Rev Time 0.00
Received By mcarsill Date 2002-08-28 Time 11:33 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2002-11-22 Cont ID  
Sent By pkrauss Date 2002-11-22 Time 09:59 Rev Time 0.35
Received By pkrauss Date 2002-11-22 Time 09:58 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2002-09-10 Cont ID  
Sent By pkrauss Date 2002-09-10 Time 11:33 Rev Time 0.35
Received By pkrauss Date 2002-09-10 Time 11:33 Sent To  
Notes
***NONE***

Review Stop MEDGAS MEDICAL GAS
Rev No 2 Status P Date 2002-09-24 Cont ID  
Sent By pschmitz Date 2002-09-24 Time 15:16 Rev Time 1.50
Received By pschmitz Date   Time   Sent To  
Notes
2002-09-24 00:00:00MED GAS REVISION, APPROVED,PES.

Review Stop MEDGAS MEDICAL GAS
Rev No 1 Status F Date 2002-09-10 Cont ID  
Sent By pschmitz Date 2002-09-10 Time 11:39 Rev Time 0.00
Received By pschmitz Date 2002-09-10 Time 11:39 Sent To  
Notes
2002-09-10 00:00:00MEDICAL GAS PLAN REVIEW, DENIED
 NFPA 99-C 1999 EDITION, LEVEL (3)
  
 (1)SHT'S 1,2 VACUUM PUMP WATER
 SUPPLY,BACK FLOW PREVENTER REQUIRED
 (RPZV).
 (2)VACUUM PUMP WASTE, DIRECT
 CONNECTION REQUIRED, SEC 4-5.2.1.3.
 (3)AIR COMPRESSOR INSTALLATION, COMPLY
 WITH SEC 4-4.1.1.3 (A) THRU (I).
 (4)VACUUM PUMPS INSTALLATION, LEVEL
 (3) SEC 4-5.2 FIG. 4-5.2.1 (A) THRU (D)
 PROVIDE A DETAIL OF SYSTEM SELECTED.
 (5)VACUUM PUMP EXHAUST, SEC 4-5.2.1.5.
 (6)VACUUM PUMP WASTE PIPING, MATERIAL
 AND SIZING SEC 4-5.2.2.3.
 (7)INDIVIDUAL TRAPS ON (FSC) SEC
 4-5.2.2.5, A SINGLE LOCATION BEFORE
 VACUUM PUMP.
 (8)PIPING INTEGRITY TEST SEC 4-5.4.1.2
 MIN. OF 150# PSI FOR 24 HOURS.
 (9)MEDICAL GAS CERTIFICATION REQUIRED
 FOR CONTRACTOR, INSTALLER, BRAZER.SEC
 4-3.1.2.10* WITH PERMIT APPLICATION.
  
 END OF COMMENTS PAUL SCHMITZ
 QUESTIONS 561-659-8096 EXT 8233.

Review Stop P PLUMBING
Rev No 2 Status P Date 2002-11-09 Cont ID  
Sent By kstevens Date 2002-11-09 Time 07:08 Rev Time 0.50
Received By kstevens Date 2002-11-09 Time 07:08 Sent To  
Notes
2002-11-09 00:00:00REVISION OK - SANITARY RISER DIAGRAM -
 BLDG DRAIN CHANGE.

Review Stop P PLUMBING
Rev No 1 Status P Date 2002-08-31 Cont ID  
Sent By kstevens Date 2002-08-31 Time 10:11 Rev Time 0.00
Received By kstevens Date 2002-08-31 Time 10:11 Sent To  
Notes
2002-08-31 00:00:00PASSED/PROVISO
  
 VENT REQUIRED FOR FLOOR DRAIN IN VACUUM
 ROOM. - FILTER SHALL BE NSF APPROVED.