| 2002-07-03 00:00:00 | BUILDING DENIED |
| | |
| | 1)A RECORDED COPY OF THE NOTICE OF |
| | COMMENCEMENT MUST BE SUBMITTED BEFORE A |
| | PERMIT CAN BE ISSUED. |
| | |
| | 2) STRUCTURE IS LOCATED IN AN "A8" FLOOD |
| | ZONE AN ELEVATION CERTIFICATE WILL BE |
| | REQUIRED. |
| | |
| | 3) PROVIDE A SOIL BEARING REPORT PER |
| | CITY AMENDMENTS TO THE 2001 FBC 1804.2.2 |
| | |
| | 4) INDICATE THE APPLICABLE INTERNAL |
| | PRESSURE COEFFICIENT ON THE PLANS AS |
| | REQUIRED BY FBC 1606.1.7. |
| | |
| | 5) THE SQUARE FOOTAGE GIVEN ON THE PLANS |
| | FOR THE GARAGE ON SHEET C-1 IS 557 SQFT. |
| | AND ON A-1 IS 427SQFT. PLEASE CLARIFY. |
| | |
| | 6) THE BONUS ROOM IS REQUIRED TO BE |
| | PERMANETLY MARK ON THE PLANS THAT IT IS |
| | NOT TO BE USED FOR SLEEPING PURPOSES. |
| | OPENINGS FROM A GARAGE DIRECTLY INTO A |
| | ROOM USED FOR SLEEPING IS NOT PERMITTED |
| | PER FBC 411.2.8. |
| | |
| | 7) THE WINDOW (H) IN THE FIRST FLOOR |
| | BATH ROOM IS REQUIRED TO HAVE TEMPERED |
| | GLASS, BECAUSE IT IS WITHIN 3 FEET |
| | HORIZONALLY OF THE TUB PER FBC 2405.2.1. |
| | |
| | 8) PLEASE CHANGE NOTE 6 UNDER GENERAL |
| | NOTES ON SHEET A-2 TO REFERENCE THE |
| | 2001 FLORIDA PLUMBING CODE. |
| | |
| | 9) SECTION B ON A-6 INDICATES R-19 |
| | INSULATION IN THE ATTIC AND THE ENERGY |
| | CALCULATIONS LISTS R-30. PLEASE CORRECT. |
| | |
| | 10) THE NAILS AND SPACING LISTED FOR THE |
| | FLOOR ON SECTION 2 ON SHEET S-2 DOES NOT |
| | CORRESPOND WITH THE FLOOR DIAPHRAGM |
| | NAILING SPECIFIED IN THE SCHEDULE. |
| | |
| | 11) THE CONDITIONED FLOOR AREA LISTED ON |
| | THE ENERGY CALCULATIONS DIFFERS FROM THE |
| | A/C AREA GIVEN ON THE PLANS. PLEASE |
| | CORRECT. |
| | |
| | 12) INDICATE ON THE PLANS THAT THE BONUS |
| | ROOM WALLS ARE INSULATED. |
| | |
| | 13) THE AREA UNDER ATTIC LISTED ON THE |
| | ENERGY CALCS. DOES NOT APPEAR TO INCLUDE |
| | THE BONUS ROOM. THE ADJACENT WOOD FRAME |
| | WALL AREA DOES NOT APPEAR TO BE CORRECT. |
| | PLEASE REVIEW AND CORRECT. |
| | |
| | 14) PROVIDE (2) CURRENT AND COMPLETE |
| | COPIES OF SBCCI OR METRO-DADE PRODUCT |
| | APPROVALS FOR: |
| | - FRONT DOOR (OUTSWING DOUBLE DOORS |
| | WITHOUT SIDELITES) |
| | - STRUCTURAL MULLIONS (THE ONES THAT |
| | WERE SUBMITTED EXPIRED ON 5-30-02) |
| | |
| | 16) PROVIDE AN INSTALLATION SCHEDULE FOR |
| | THE STORM PANELS. INDICATE THE TYPE OF |
| | FASTENER AND MOUNTING OPTIONS THAT WILL |
| | BE USED (CIRCLE OR HIGHLIGHT ON THE |
| | PRODUCT APPROVAL DRAWINGS). THIS |
| | INFORMATION IS REQUIRED AT TIME OF |
| | PERMIT OR A SEPARATE PERMIT WILL BE |
| | REQUIRED WITH ADDITIONAL PERMIT FEES. |
| | |
| | IF YOU HAVE ANY QUESTIONS PLEASE CALL: |
| | ROBERT MCDOUGAL |
| | BLDG. PLAN REVIEW |
| | (561)659-8096 EXT.8202 |