| Plan Review Stops For Permit 02051594 |
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
1 |
Status |
P |
Date |
2002-05-30 |
|
|
Cont ID |
|
| Sent By |
mamini |
Date |
2002-05-30 |
Time |
10:21 |
Rev Time |
3.00 |
| Received By |
mamini |
Date |
2002-05-30 |
Time |
10:20 |
Sent To |
|
|
| Notes |
| 2002-05-30 00:00:00 | PASSED WITH PROVISOS: | | | 1. PLEASE NOTE THAT ANY WORK WITHIN | | | PUBLIC R.O.W WOULD REQUIRE APPROVAL AND | | | PERMIT FROM CITY ENGINEER OFFICE , | | | 659-8040. | | | 2. ALL OFF STREET MUST BE PAINTED WITH | | | DOUBLE 4" WHITE FOR REGULAR PARKING | | | STALLS. | | | 3. POLLUTION / EROSION PLANS MUST BE | | | INSTALLED IN THE FIELD PRIOR TO ANY | | | SITE /EARTH WORKS. | | | 4. CONTRACTOR TO VERIFY THE EXACT | | | LOCATION, DEPTH OF THE EXISTING SANITARY | | | SEWER AT LOCATION OF THE PROPOSED POND, | | | REMOVE AND RELOCATE AS MUCH AS REQUIRE | | | TO ALLOW FOR CONSTRUCTION OF THE POND | | | AND TO PROVIDE ADEQUATE COVER AND | | | CLEARANCES WITH OTHER UNDERGROUND | | | UTILITIES. | | | 5. DRIVEWAY APPROACHES MUST BE | | | CONSTRUCTED PER CITY OF WPB STANDARD, | | | SEE ATTACHED. | | | IF ANY QUESTIONS PLEASE CONTACT 659-8096 | | | EXT. 8492 MOHAMMAD R. AMINI |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2002-07-03 |
|
|
Cont ID |
|
| Sent By |
mcarsill |
Date |
2002-07-03 |
Time |
16:08 |
Rev Time |
0.00 |
| Received By |
mcarsill |
Date |
2002-07-03 |
Time |
16:08 |
Sent To |
|
|
| Notes |
| 2002-07-03 00:00:00 | CLEARANCE TO NEW FIRE HYDRANT IS TO | | | BE AT LEAST SEVEN FEET SIX INCHES TO | | | THE FRONT AND SIDES. FOUR FEET | | | CLEARANCE IS REQUIRED TO THE REAR. | | | | | | MIKE CARSILLO, ASSISTANT FIRE MARSHAL | | | 659-8096,EXT.8497 | | | 835-2910 |
|
|
|