| 2002-07-10 00:00:00 | BUILDING DENIED |
| | |
| | 1) A RECORDED COPY OF THE NOTICE OF |
| | COMMENCEMENT MUST BE SUBMITTED BEFORE A |
| | PERMIT CAN BE ISSUED. |
| | |
| | 2) PRODUCT APPROVALS FROM TWO DIFFERENT |
| | STORM PANEL COMPANIES WERE SUBMITTED. |
| | PLEASE INDICATE WHICH ONE YOU WILL BE |
| | USING AND REMOVE THE OTHER. NOTE THE |
| | PRODUCT APPROVAL FOR THE EASTERN METAL |
| | SUPPLY STORM PANELS ARE NOT COMPLETE. |
| | |
| | 3) INDICATE THE INSTALLATION OPTIONS |
| | THAT WILL BE USED BY CIRCLING THEM ON |
| | THE PRODUCT APPROVAL DRAWINGS. |
| | |
| | 4) TAPCONS ARE NOT AN ACCEPTABLE ANCHOR |
| | FOR ATTACHMENT TO WOOD FRAME |
| | INSTALLATIONS. SEE SHEET 6 OF THE TOWN & |
| | COUNTRY PRODUCT APPROVAL. |
| | |
| | 5) THE INSTALLATION SCHEDULE IS NOT |
| | FILLED OUT CORRECTLY. PLEASE REVISE. |
| | - THE SHUTTER HEIGHT WILL BE A MINIMUM |
| | OF 1-1/2" LARGER THAN THE OPENING DUE TO |
| | THE 3/4" EDGE DISTANCE REQUIREMENT FOR |
| | FASTENERS.SEE SHEET 6. |
| | - THE SHUTTER SPAN IS THE OPENING |
| | DIMENSION PARALLEL TO THE DIRECTION THE |
| | SHUTTER IS MOUNTED. |
| | - NO STORM BARS ARE REQUIRED FOR THE |
| | SPANS INDICATED. |
| | - NO HEADER REINFORCEMENT OR STORM PANEL |
| | BOLTING WILL BE REQUIRED. |
| | TYPICALLY EACH WINDOW OPENING IS GIVEN A |
| | NUMBER AND EACH NUMBER IS LISTED IN THE |
| | SCHEDULE ALONG WITH THE INFORMATION FOR |
| | THAT OPENING. DOUBLE WINDOWS ARE LISTED |
| | AS ONE OPENING. I HAVE ATTACHED A COPY |
| | OF A KEY PLAN AND SCHEDULE FOR YOU TO |
| | USE AS A GUIDE. |
| | |
| | 6) THE PRODUCT APPROVALS FOR THE WINDOW |
| | MULLIONS ARE NOT COMPLETE AND THE |
| | DRAWINGS ARE ILLEGIBLE. TWO COPIES ARE |
| | REQUIRED. |
| | |
| | 7) IF YOU DO NOT WANT THE ELECTRICAL |
| | PERMIT AT THIS TIME, PLEASE INDICATE ON |
| | REQUEST FOR PROPOSAL (WORK DESCRIPTION) |
| | THAT ITEM #3 WILL BE APPLIED FOR UNDER A |
| | SEPARATE PERMIT. |
| | |
| | ROBERT MCDOUGAL |
| | BLDG. PLAN REVIEW |
| | (561)659-8096 EXT.8202 |