| 2001-01-22 00:00:00 | BUILDING PLAN REVIEW: |
| | 1)-FL. S.S. 481 TO HAVE ARCHITEECT TO |
| | SIGN/ SEAL & DATE DRAWINGS. |
| | 2)- 1997 FL ENERGY EFFICIENCY CODE 400.0 |
| | REQUIRES ENERGY CODE COMPLIANCE DOCUMENT |
| | 3)- SBC 1804.2 SOILS REPORT MINIMUM |
| | SOIL BEARING. |
| | 4)- SHEET A-3 DETAIL A REQUIRES A VAPOR |
| | BARRIER AT SLAB.SBC 103.7..3.7 TREATED |
| | SOIL SHALL BE COMPLETELY COVERED WITH A |
| | VAPOR BARRIER FROM THE SUN & RAIN WITHIN |
| | 2 HRS. OF CHEMICAL APPLICATION. |
| | 5)- SHEET A-3 DETAIL B WILL ALSO REQUIRE |
| | ADDITIONAL TERMITE CHEMICAL SOIL TREAT- |
| | MENTS SHALL BE APPLIED UNDER ALL EXTER- |
| | IOR CONCRETE ON GRADE THAT ARE WITHIN ON |
| | ONE FOOT OF THE PRIMARY STRUCTURE SIDE- |
| | WALLS.SBC 103.7.3.5 |
| | 6)- SBC 1606.2.6.2- COMPONENTS & CLAD- |
| | DING, ALL GLAZED OPENINGS WILL REQUIRE |
| | TESTING 16606.4.1/1707.4.1 FOR LARGE |
| | MISSLE RESISTANCE, IF THE PRODUCT WASN'T |
| | TESTED STORM SHUTTERS WILL BE REQUIRED |
| | MEETING THIS REQUIREMENT. A SHUTTER |
| | SCHEDULE FOR ATTACHMENT AND A DIAGRAM OF |
| | OPENINGS TYING THE 2 TOGETHER.ALL EXTER- |
| | IOR DOOR OPENINGS WUOLD ALSO HAVE TO |
| | HAVE PROOF OF TESTING. |
| | 7)- ROOFING SBC 1606.2.6.2- WILL ALSO |
| | REQUIRE TESTING REPORTS, DADE COUNTY OR |
| | SBCCI REPORT WILL BE REQUIRED,2 COPIES. |
| | 8)- SBC 104.2.2- ADDITIONAL INFORMATION |
| | WILL BE REQUIRED FOR THE CUPOLA, IS THIS |
| | MEETING THE REQUIREMENTS OF 1606.2D FOR |
| | WIND? TEST RESULTS SHOWING POSITIVE & |
| | NEGATIVE PRESSURES TESTED FOR? |
| | 9)- AWNINGS REQUIRE A SEPERATE PERMIT, |
| | THEY WILL HAVE TO HAVE PROOF OF FIRE |
| | RETARDANT FABRIC, FRAMES TO HAVE ENGIN- |
| | EERING. |
| | 10)- FIRESTOPPING- SBC 2305.1.4.1- |
| | FIRE STOPPING WILL BE REQUIRED AT FLOOR |
| | AND CEILING LINE. |
| | 11)-SBC 2309.6 ATTIC ACCESS REQUIRED. |
| | 12)- SBC 803.3 REQUIRES A MINIMUM FINISH |
| | ROOM SCHEDULE IN ACCORDANCE WITH ASTM - |
| | E-84, WITH FLAMESPREAD & SMOKE DEVELOP- |
| | MENT. |
| | 13)- SBC 104.2.2- ADD. INFORMATION RE- |
| | QUIRED, DROPPED CEILING, WHAT MATERIAL |
| | IS THE DROPPED CEILING MADE OF? HOW |
| | OFTEN IS THE CEILING SUPPORTED AND BY |
| | WHAT MEANS IS THE CEILING SUPPORTED? |
| | |
| | BUILDING PLAN REVIEW |
| | JIM WITMER |
| | (561) 659- 8096 EX 8412 |