| Miscellaneous Information / Notes |
| REROOF 5800SQFT TILE |
| |
| |
| |
| 11/29/22 PERMIT ISSUED. LEM |
| 11/29/22 MITIGATION LTR RECEIVED WITH DIGITAL SIG. |
| RELEASED INSPECTION HOLD. CT |
| 11/28/22 REVIEWS COMPLETE, WAITING ON UPDATED |
| CONTRACTOR INFO TO ISSUE PERMIT. LEM |
| 11/28/22 CONTRACTOR AGREED TO PROVIDE MITIGATION |
| LTR W/DIGITAL SIG PRIOR TO INSPECTIONS. PLACED AN |
| INSP. HOLD ON PERMIT. LTR TO BE E-MAILED TO CT. |
| 11/18/22 SPOKE WITH CONTRACTOR, INDIVIDUAL IN |
| CHARGE OF THIS SUBMITTAL WILL BE IN ON MONDAY. |
| WILL PROPSE PLACING AN INSPECTION HOLD PENDING |
| RECEIPT OF ENGINEER'S LETTER WITH VALID SIG. CT |
| 11/18/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 11/18/22 SIGNATURE REVIEW FAILED. JNB |
| 11/18/22 BUILDING REVIEW FAILED. JNB |
| 11/13/22 RESUB RECEIVED, INCOMING COMPLETE AO |
| 11/8/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 11/8/22 SIGNATURE REVIEW FAILED. JNB |
| 11/8/22 BUILDING REVIEW FAILED. JNB |
| 10/31/22 RESUB RECEIVED, INCOMING COMPLETE AO |
| 10/31/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT. CP |
| 10/31/22 CONTRACTOR LICENSE & INSURANCE NEEDS |
| UPDATING. JNB |
| 10/31/22 SIGNATURE REVIEW FAILED. JNB |
| 10/31/22 BUILDING REVIEW FAILED. JNB |
| 10/28/22 PLANS UPLOADED, INCOMING COMPELTE.CD |
| 10/27/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |