| Miscellaneous Information / Notes |
| INTERIOR RENOVATION TO SUITE 100 |
| |
| |
| |
| |
| 12/16/22 CC ISSUED AND EMAILED TO ERIC ALFREDSON. |
| SCANNING FOR FILENET. ATTACHED IN C+. FILED UNDER |
| THE LETTER H. SD |
| 11/2/22 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS. CP |
| 11/1/22 PLAN REVIEW COMPLETE WAITING ON FEES AND |
| CONT UPDATE. CP |
| 11/1/22 RESUB RECEIVED, INCOMING COMPLETE AO |
| 10/31/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT. CP |
| 10/25/22, PASS FIRE, CRW, WITH PROVISO COMMENTS |
| 10/24/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 10/24/22 REJECTED, REVISED PLANS WERE UPLOADED TO |
| SUPP. DOCS. FOLDER & NOT VERSIONED. EMAILED |
| APPLICANT TO REUPLOAD. AO |
| 10/19/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 10/7/22 START EARLY DOC & SUB APPS UPLOADED INTO |
| PROJECTDOX. PAPER ROUTED TO OCTOBER STORAGE BOX IN |
| SCANNING.CD |
| 10/5/22 ISSUED LETTER GRANTING AUTHORIZATION FOR |
| EARLY START UP TO FIRST INSPECTION. RB |
| 10/5/22 RECEIVED CONTRACTOR LETTER REQUESTING |
| AUTHORIZATION FOR EARLY START UP TO FIRST |
| INSPECTION. RB |
| 8/25/22, PASS FIRE, CRW, WITH PROVISO COMMENTS |
| 8/24/22 PLANS UPLOADED, PARTIAL FEES PAID, |
| INCOMING COMPLETE. PAPER ROUTED TO AUGUST STORAGE |
| BOX IN SCANNING.CD |
| 8/24/22 CHANGED FROM PAPER TO DIGITAL.CD |
| 8/23/22 ROUTED TO DIGITAL SHOLDER |