| Miscellaneous Information / Notes |
| REROOF BUR 30# TILE SEAL, CONCRETE TILE |
| |
| |
| |
| |
| 9/19/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, PERMIT CARD UPLOADED. LEM |
| 9/19/22 BUILDING REVIEW PASSED. JNB |
| 9/16/22 RESUB RECEIVED, INCOMING COMPLETE AO |
| 9/15/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
| RESUBMIT AO |
| 9/8/22 BUILDING REVIEW FAILED. JNB |
| 9/6/22 SIGNATURE REVIEW OF PAPER PLANS/DOCUMENTS |
| PASSED AND ROUTED TO STORAGE.MP |
| 9/2/22 RESUB DOCS ROUTED TO S1 FOR SIGNATURE |
| REVIEW.CD |
| 8/30/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 8/30/22 CUSTOMER RESUB TO ADDRESS DENIED COMMENTS |
| ROUTED TO DIGITAL SHOLDER |
| 8/26/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 8/26/22 SIGNATURE REVIEW FAILED. JNB |
| 8/26/22 BUILDING REVIEW FAILED. JNB |
| 8/17/22 APPLICANT RESUBMITTED DIGTALLY,INCOMING |
| COMPLETE AO |
| 8/9/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 8/9/22 SIGNATURE REVIEW FAILED. JNB |
| 8/9/22 BUILDING REVIOEW FAILED. JNB |
| 8/3/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 7/29/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
| RESUBMIT AO |
| 7/21/22 SIGNATURE REVIEW FAILED. JNB |
| 7/21/22 BUILDING REVIEW FAILED. JNB |
| 7/20/22 PLANS UPLOADED,INCOMING COMPLETE.CD |
| 7/7/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |