| Miscellaneous Information / Notes |
| NEW CONSTRCUTION OF A SFR |
| |
| |
| 07/13/2023 CONTRACTOR ADDED JO. |
| 6/27/23 RECEIVED LETTER REQUEST FROM ALLEN GAST TO |
| REMOVE EXISTING CONTRACTOR.BB |
| 12/20/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, PERMIT CARD UPLOADED. LEM |
| 12/1/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 11/16/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
| RESUBMIT AO |
| 10/30/22 IMPACT FEE QUEST UPLOADED. PBCGOV |
| EMAILED, PER SH AO |
| 10/14/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 9/29/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 8/23/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 8/8/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 8/8/22 VALUE VERIFIED. CT |
| 8/8/22 FLOOD ZONE X. CT |
| 8/8/22 DEF. FEILDS COMPLETE. CT |
| 8/8/22 PROVISO ON PG SP-101: SITE WALLS. CTR |
| 7/7/22 PLANS CORRECTED,INCOMING COMPLETE.CD |
| 7/6/22 REJECTED, NEED TO REUPLOAD CORRUPT FILE |
| "NOA - 21-0917.03 - CGI FRENCH DOORS.PDF".CD |
| 6/28/22 APPLICANT INVITED TO PAY FEES AND UPLOAD |
| PLANS AO |