| Miscellaneous Information / Notes |
| ADDITION OF ROOM ON BACK OF STRUCTURE |
| |
| |
| |
| 10/4/22 PERMIT ISSUED. LEM |
| 9/20/22 REVIEWS COMPLETE, WAITING ON IMPACT TO |
| REVIEW. LEM |
| 9/09/22 RESUB RECEIVED, INCOMING COMPLETE AO |
| 9/7/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 9/6/22 PASSED BY FIRE.PML |
| 9/02/22 RESUB RECEIVED,PLANS VERSIONED,INCOMING |
| COMPLETE AO |
| 8/26/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 8/18/22 PASSED BY FIRE.PML |
| 8/12/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 7/29/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 7/12/22 RESUB PASSED W/COMMENT BY FIRE. BD |
| 7/11/22 APPLICANT RESUBMITTED DIGITALLY,PLANS |
| VERSIONED,INCOMING COMPLETE AO |
| 6/1/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 4/29/22 FAILED BY FIRE WITH COMMENTS.PML |
| 4/22/22 PLANS UPLOADED,INCOMING COMMPLETE.CD |
| 4/4/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |