| Miscellaneous Information / Notes |
| INTERIOR RENOVATION - MIDDLE BAY EXAM ROOMS. |
| |
| |
| |
| |
| |
| |
| |
| 2/27/23 ADDRESS UPDATED TO 481 SPENCER DR |
| 7/22/22 CC ISSUED AND EMAILED TO MIKE RIEHL. |
| SCANNING FOR FILENET. ATTACHMENT IN C+. FILED |
| UNDER "M". KP |
| 7/22/22 THIS WAS TO BE PHASE TWO, BUT TIMING |
| DIDN'T ALLOW FOR THE DRAWINGS TO BE PRDUCED TO |
| SHOW PHASING, SO THIS MIDDLE SECTION OF THE SPACE |
| HAS ITS OWN PERMIT BUT ALL INSPECTIONS WERE DONE |
| UNDER 21050958. DB |
| 7/21/22 PERMIT ISSUED. LEM |
| 7/20/22 REVIEWS COMPLETE, WAITING ON FEES TO ISSUE |
| PERMIT AO |
| 7/19/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 7/12/22 DB VERSIOEND ALL PLANS, TASK DONE & |
| INCOMING COMPLETE AO |
| 7/11/22 THE PROJECTDOX TASK WAS NOT COMPLETE, NO |
| INCOMING DONE. PLANS WERE INCORRECTLY UPLOADED TO |
| SIGNATURE FOLDER, NEED TO BE VERSIONED AND DELETED |
| FROM SIGNATURE (SEE PROJECTDOX INSTRUCTIONS). |
| REJECTED BACK TO APPLICANT, WILL BACKDATE TO 7/6 |
| IF THEY UPLOAD TIMELY SH |
| 7/6/22 PLANS UPLOADED INCOMING COMPLETE. DB |
| 7/6/22 ADJUSTED VALUE FOR MIDDLE BAY. THE PERMIT |
| FEE SHOULD BE $2783.42 AND FEES WERE ADJUSTED TO |
| THIS AMOUNT. DB |
| 7/1/22 CHANGED FROM REVISION TO COM-INT. DB |
| 3/10/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 2/17/22 REV PASS FIRE. BD |
| 2/14/22 APPLICANT RESUBMITTED DIGITALLY,PLANS |
| VERSIONED. APPLICANT ADDED MEP PLANS. INCOMING |
| COMPLETE AO |
| 1/24/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 1/18/22 APPLICANT RESUBMITTED DIGITALLY,PLANS |
| VERSIONED,INCOMING COMPLETE AO |
| 12/15/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 12/3/21 PASS FIRE JCC |
| 12/2/21 PLANS VERSIONED, INCOMING COMPLETE. LEM |
| 11/24/21 APPLICANT INVITED TO PAY FEES AND UPLOAD |
| PLANS / DOCUMENTS. CC |