| Miscellaneous Information / Notes |
| WAREHOUSE EXPANSION - ADDITION TO EXISTING |
| BUILDING |
| |
| |
| |
| |
| 10/13/22 PERMIT ISSUED. LEM |
| 10/4/22 REVIEWS COMPLETE, WAITING ON FEES TO ISSUE |
| PERMIT. LEM |
| 7/13/22 REVIEWS COMPLETE. IMPACT FEE QUEST |
| UPLOADED. PBCGOV EMAILED AO |
| 7/12/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT. CP |
| 7/11/22 - ZONING APPROVED WITH PROVISO. CONTACT |
| PERMIT LIBRARIAN TO PROCESS. LL |
| 6/16/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
| COMPLETE AO |
| 6/7/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 6/3/22 - ZONING FAILED. LL |
| 5/22/22 RESUBMITTAL RECEIVED, INCOMING COMPLETE SH |
| 3/9/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 3/8/22 - ZONING FAILED. LL |
| 2/18/22 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 1/20/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 12/27/21 - ZONING FAILED. LL |
| 12/3/21 PASS FIRE JCC |
| 12/2/21 PLANS CORRECTED, INCOMING COMPLETE.CD |
| 11/29/21 PLANS REJECTED, NEED TO PROPERLY NAME THE |
| 26 PLAN SHEETS IN THE DRAWING FOLDER.CUSTOMER |
| EMAILED TO CORRECT.CD |
| 11/22/21 APPLICANT INVITED TO PAY FEES AND UPLOAD |
| PLANS / DOCUMENTS. CC |