| Miscellaneous Information / Notes |
| RENOVATE INTERIOR INCLUDING NEW MEP EQUIP, |
| FRAMING, DRYWALL, NEW LOBBY, CLASSROOMS, BREAK |
| ROOM & OFFICES |
| |
| |
| |
| 6/27/23 TCO3 FEE PAID. CERTIFICATE ISSUED AND |
| EMAILED TO JONI MORGAN. SCANNING FOR FILENET. |
| ATTACHEMNT IN C+. FILED UNDER "Q". KP |
| 6/20/23 TCO3 FEE APPLIED AND EMAILED JONI MORGAN. |
| KP |
| 6/15/23 CBAA GRANTED TCO EXTENSION WITH THE |
| CONDITION THAT BUILDING OFFICIAL, ROBERT BROWN |
| WILL REVIEW INFO PROVIDED ON FIELD APPLIED COATING |
| WITH CHIEF MECH. INSP. H. MOSER AND PROVIDE INPUT |
| ON IF THE CITY IS OK WITH THE COATING. |
| CBAA DOCUMENTS ATTACHED. |
| 6/1/23 CASE 1467 SCHEDULED FOR 6/15/23 CBAA |
| MEETING. SEE ATTACHED DOCUMENTS. KP |
| 6/1/23 CBAA FEE PAID. SCHEDULE FOR 6/15/23 CBAA |
| MEETING. KP |
| 6/1/23 CBAA APPLICATION RECEIVED AND FEE APPLIED. |
| KP |
| 2/21/23 EMAILED CBAA APPLICATION TO JONI MORGAN. |
| KP |
| 11/16/22 EMAILED TCO EXTENSION TO CONTRACTOR. RB |
| 11/16/22 RECEIVED CONTRACTOR'S REQUEST FOR TCO |
| EXTENSION. RB |
| 8/17/2022 TCO ISSUED STUDENTS AND STAFF |
| 8/10/22 ADDED TCO FEE AS REQUESTED BY JM. 200.00 |
| BALANCE ALREADY EXISTED FROM FIRE RE-INSPECTION |
| FEE. DB |
| 8/9/22 ISSUED TCO VIA EMAIL. SIGNED ORIGINAL IS IN |
| CO BOX UNDER "Q". RB |
| 8/9/22 RECEIVED TCO REQUEST FORM. RB |
| 3/31/22 DEDUCTED VALUE OF GENERATOR (50,000) FROM |
| FEES PAID, TRANSFERRED TO GENERATOR PERMIT. LEM |
| 3/7/22 REVIEWS COMPLETE, WAITING ON FEES TO ISSUE |
| PERMIT. LEM |
| 3/4/22 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 3/3/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 2/28/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 2/27/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT. CP |
| 2/16/22, PASS FIRE, CRW |
| 2/15/22 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 2/1/22 ISSUED LETTER GRANTING AUTHORIZATION TO |
| START WORK UP TO FIRST INSPECTION PRIOR TO PERMIT |
| ISSUANCE. RB |
| 1/30/22 CONTRACTOR SUBMITTED LETTER REQUESTING |
| AUTHORIZATION TO START WORK UP TO FIRST INSPECTION |
| PRIOR TO PERMIT ISSUANCE. RB |
| 1/28/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 1/11/22, PASS FIRE, CRW |
| 1/10/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 12/17/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 11/4/21, PASS FIRE, CRW, PROVISO NOTES (1) IF |
| KITCHEN EQUIPMENT PRODUCES SMOKE OR GREASE LADEN |
| VAPOR A COMMERCIAL EXHAUST/SUPPRESSION WILL BE |
| REQUIRED. (2) ALL INTERIOR FINISHES TO COMPLY WITH |
| NFPA 101 CHAPTER 10. |
| |
| 11/3/21 PLANS UPLOADED,INCOMING COMPLETE.CD |
| 10/29/21 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |
| |
| |
| |
| |