| Miscellaneous Information / Notes |
| NEW ROOF AND LABOR - BRIDGE TENDER HOUSE LOCATED |
| IN FDOT RIGHT-OF-WAY ON SOUTHERN BLVD BRIDGE. |
| |
| |
| |
| 3/30/22 PERMIT ISSUED. LEM |
| 3/23/22 REVIEWS COMPLETE, WAITING ON CONTRACTOR TO |
| REGISTER TO ISSUE PERMIT. LEM |
| 3/23/22 BUILDING REVIEW PASSED. JNB |
| 3/1/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 3/1/22 SIGNATURE REVIEW PASSED. JNB |
| 3/1/22 BUILDING REVIEW PASSED. JNB |
| 2/16/22 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 12/2/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 12/1/21 SIGNATURE REVIEW FAILED. JNB |
| 12/1/21 BUILDING REVIEW FAILED. JNB |
| 11/30/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 11/2/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 11/2/21 SIGNATURE REVIEW FAILED. JNB |
| 11/2/21 BUILDING REVIEW FAILED. JNB |
| 11/01/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 10/28/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 10/25/21 PLANS CORRECTED, INCOMING COMPLETE. MOVED |
| COMPLETE BRIDGE PLAN TO SIGNATURE INCASE REVIEWERS |
| MAY WANT TO SEE.CD |
| 10/21/21 REJECTED PLANS,NEED TO SEPARATE AND |
| PROPERLY NAME PLAN SHEETS. ALSO, WORK DESCRIPTION |
| ON APPLICATION SAYS "NEW ROOF & LABOR". THE |
| UPLOADED PLANS ARE FOR AN ENTIRE BRIDGE CONTROL |
| HOUSE. CUSTOMER EMAILED TO CORRECT.CD |
| 9/27/21 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |