| LANDSCAPE PLANS |
| |
| |
| |
| 7/21/22 PERMIT ISSUED. LEM |
| 7/18/22 REVIEWS COMPLETE, WAITING ON FEES AND |
| UPDATED CONTRACTOR INFO TO ISSUE PERMIT. LEM |
| 7/18/22 APPROVED WITH CONDITIONS AND MARK UPS ON |
| PLAN SHEETS. RC |
| 5/27/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
| COMPLETE AO |
| 4/26/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 4/26/22 FAILED LANDSCAPE REVIEW RC |
| 4/20/22 COST ESTIMATE SUBMITTED FROM LANDSCAPE |
| ARCHITECT TO CHANGE PERMIT VALUE TO $675,722.00 RC |
| 4/8/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
| COMPLETE AO |
| 3/14/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 3/14/22 FAILED REVIEW, NEED TO SUBMIT A FULL |
| REVISED PLAN SET AND HAVE THE PREVIOUS PLANS |
| DELETED. SEE REVIEW COMMENTS. RC |
| 2/23/22 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 10/28/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 10/27/21 LANDSCAPE REVIEW FAILED, SEE COMMENTS. RC |
| 9/30/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 9/28/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 9/17/21 FAILED LANDSCAPE REVIEW, SEE COMMENTS. RC |
| 9/7/21 REVIEW OF SIGNATURE AND SEAL ON PAPER PLANS |
| AND/OR DOCUMENTS APPROVED AND PLANS ROUTED TO |
| STORAGE/CLC |
| 9/7/21 PLANS UPLOADED, INCOMING COMPLETE. ADDED PP |
| PER HOLD REQUEST. PAPER ROUTED TO CCOLE FOR |
| SIGNATURE REVIEW.CD |
| 9/7/21 CHANGED FROM PAPER TO DIGITAL.CD |