| Miscellaneous Information / Notes |
| INTERIOR BUILD OUT NADG OFFICE |
| |
| |
| 11/15/22 CO ISSUED AND EMAILED TO TONY MAZZOTTA |
| AND ADAM SPIEWAK. SCANNING FOR FILENET. ATTACHMENT |
| IN C+. FILED UNDER "J". KP |
| 8/8/2022 REQUEST FOR TCO EXTENSION RECEIVED. FEE |
| POSTED AND PAID. TCO EXTENSION ISSUED AND EMAILED |
| TO TONY MAZOTTA. REG |
| 5/16/2022 TCO ISSUED SENT TO TONY MAZZOTTA SEE |
| ATTACHED REG |
| 4/29/2022 RECEIVED REQUEST FOR TCO FEE IS PAID AND |
| STOCKING WAS NOT ISSUED, SEE ATTACHED REG |
| 04/19/2022 RECEIVED REQUEST TO STOCK, FEE APPLIED |
| SEE ATTACHED REG |
| |
| 11/22/21 REVIEWS COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, PERMIT CARD UPLOADED. LEM |
| 11/3/21 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 10/25/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 10/20/21 ISSUED LETTER AUTORIZING EARLY START UP |
| TO FIRST INSPECTION PRIOR TO ISSUANCE OF THE |
| PERMIT. RB |
| 10/20/21 RECEIVED LETTER FROM CONTRACTOR |
| REQUESTING AUTORIZATION FOR EARLY START UP TO |
| FIRST INSPECTION PRIOR TO ISSUANCE OF THE PERMIT. |
| RB |
| 10/14/21 RECEIVED CHANGE OF CONTRACTOR, PROCESSED. |
| LEM |
| 10/8/21 PASSED BY FIRE.PML |
| 10/7/21 APPLICANT RESUBMITTED DIGITALLY,PLANS |
| VERSIONED,INCOMING COMPLETE AO |
| 10/4/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 8/26/21 PASSED BY FIRE.PML |
| 8/19/21 PLANS UPLOADED,INCOMING COMPLETE.CD |
| 8/17/21 APPLICANT INVITED TO UPLOAD PLANS OR |
| DOCUMENTS AND PAY FEES. CC |