| Miscellaneous Information / Notes |
| NEW CONSTRUCTION OF A 25 STORY, 41 UNIT |
| CONDOMINIUM TOWER WITH 3 AMENITY LEVELS, AND TWO |
| LEVEL GARAGE W/ 133 TOTAL SPACES |
| |
| |
| 10/18/22 PERMIT ISSUED. LEM |
| 10/17/22 REVIEWS COMPLETE, WAITING ON FEES AND |
| CONTRACTOR'S SIGNATURE TO ISSUE PERMIT. LEM |
| 10/14/22 REVIEWS COMPLETE, WAITING ON IMPACT |
| STAMP. LEM |
| 9/21/22 RESUB RECEIVED, INCOMING COMPLETE AO |
| 9/16/22 REVIEWS COMPLETE,APPLICANT NEEDS TO |
| RESUBMIT SH |
| 8/18/22 IMPACT FEE QUEST UPLOADED. PBCGOV EMAILED |
| PER SH AO |
| 8/8/22 APPLICANT RESUBMITTED DIGTALLY,INCOMING |
| COMPLETE AO |
| 8/8/22 REJECTED, DOCUMENTS UPLOADED W ERRORS AND |
| ARE NOT ACCESSIBLE. EMAILED APPLICANT TO REUPLOAD |
| AO |
| 7/25/22 CORR, APPLICANT NEEDS TO RESUBMIT SH |
| 6/2/22 PASSED BY FIRE.PML |
| 5/22/22 RESUBMITTAL RECEIVED, INCOMING COMPLETE SH |
| 5/18/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 3/22/22 PASSED BY FIRE.PML |
| 3/10/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
| COMPLETE AO |
| 3/9/22 REJECTED TASK BACK TO CUSTOMER, REVISED |
| PLANS WERE NOT VERSIONED. EMAILED APPLICANT TO |
| REUPLOAD. AO |
| 2/10/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 12/17/21 PLANS UPLOADED, INCOMING COMPLETE. LEM |
| 12/3/21 REJECTED BACK TO APPLICANT TO UPLOAD |
| REVISED PAGES SH |
| 7/30/21 APPLICANT INVITED TO UPLOAD PLANS OR |
| DOCUMENTS AND PAY FEES. CC |