| Miscellaneous Information / Notes |
| BUILD NEW SFR |
| |
| |
| CHANGE PERMIT TYPE TO BLD RES |
| SEPERATE DEMO PERMIT REQUIRED |
| |
| |
| |
| 2/8/23 CO ISSUED AND EMAILED TO HAROLD DAVIDSON. |
| SCANNING FOR FILENET. ATTACHED IN C+. FILED UNDER |
| THE LETTER H. SD |
| 4/8/22 PERMIT ISSUED. LEM |
| 4/7/22 REVIEWS COMPLETE, WAITING ON FEES TO ISSUE |
| PERMIT. LEM |
| 3/30/22 REVIEWS COMPLETE, WAITING ON IMPACT. LEM |
| 3/24/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 3/3/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 1/20/22 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 1/6/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 1/06/22 DEF. FIELDS COMPLETE. CT |
| 1/06/22 ADJUST VALUE TO $142,974 PER THE ICC BLDG. |
| VALUATION DATA. CT |
| 12/09/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 11/29/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 11/27/21 ROOFING PROVISO ON PG A-4. CT |
| 11/27/21 IMPACT FEES DUE. CT |
| 10/6/21 PLANS UPLOADED,INCOMING COMPLETE.DID NOT |
| REMOVE ZONING DUE TO NEW A/C UNIT W/SHRUBS AROUND |
| IT.CD |
| 6/3/21 EMAILED CPUELL TO UPDATE OWNER. LEM |
| 6/3/21 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |