| Miscellaneous Information / Notes |
| COOLING TOWER REPAIRS. REPAIR CONCRETE BEAMS |
| |
| |
| 2/2/22 CC ISSUED AND EMAILED TO |
| [email protected]. SCANNNING FOR FILENET. |
| ATTACHMENT IN C+. FILED UNDER "O". KP |
| 5/20/21 REVIEWS COMPLETE, WAITING ON FEES AND |
| UPDATED CONTRACTOR INFO TO ISSUE PERMIT. LEM |
| 5/20/21 - ZONING PASS. CONTACT PERMIT LIBRARIAN TO |
| PROCESS OUT. LL |
| 05/13/2021 ORIGINAL SIGNED AND SEALED PAPER |
| DOCUMENTS ROUTED TO STORAGE.ME |
| 5/12/21 RESUB UPLOADED TO PROJECTDOX. PAPER |
| ORIGINALS ROUTED TO ME.INCOMING COMPLETE AO |
| 5/12/21 RESUB ADDRESSING COMMENTS ROUTED TO |
| INCOMING. TSG |
| 3/30/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 3/30/21 - ZONING FAILED. CONTACT PERMIT LIBRARIAN |
| TO PROCESS OUT. LL |
| 03/16/2021 ORIGINAL SIGNED AND SEALED PAPER |
| DRAWINGS ROUTED TO STORAGE.ME |
| 03/16/21 RESUB UPLOADED TO PROJECTDOX, PAPER |
| ORIGINALS ROUTED TO ME. INCOMING COMPLETE AO |
| 3/15/21 CHARLIE RESUB TO ADDRESS DENIED COMMENTS |
| SENT TO SCANNING TO BE CONVERTED TO A DIGITAL |
| PERMIT SL |
| |
| 2/8/21 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. CP |
| 2/5/21 - ZONING FAILED. LL |
| 1/27/21 PLANS UPLOADED, INCOMING COMPLETE AO |
| 1/27/21 UPLOADED TO PROJECTDOX. PAPER ORIGINALS |
| ROUTED TO ME AO |
| 1/27/21 FEES PAID ROUTED TO INCOMING. TSG |