| Miscellaneous Information / Notes |
| INSTALL 22KW GENERAC GENERATOR |
| |
| |
| |
| |
| 4/19/21 PERMIT ISSUED. LEM |
| 4/19/21 REVIEWS COMPLETE, WAITING ON OWNER |
| SIGNATURE TO ISSUE PERMIT. LEM |
| 04/15/21 RESUB RECEIVED, INCOMING COMPLETE AO |
| 4/7/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 04/05/21 RESUB RECEIVED, INCOMING COMPLETE AO |
| 3/25/21 REJECTED TASK BACK TO CUSTOMER. LEM |
| 3/23/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 03/22/21 RESUB RECEIVED, INCOMING COMPLETE AO |
| 3/19/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 3/19/2021 CLOSED THE INCOMING STOP/PERMIT |
| LIBRARIANS INFORMED.PV |
| 3/19/2021 SIGNATURE REVIEW FAILED.PV |
| 03/18/21 RESUB RECEIVED, INCOMING COMPLETE AO |
| 3/17/21 REJECTED TASK BACK TO CUSTOMER, NOTHING |
| UPLOADED. LEM |
| 3/17/21 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. CP |
| 2/24/21 RESUBMIT RECEIVED, INCOMING COMPLETE. CC |
| 1/22/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 01/08/21 RESUBMIT RECEIVED, INCOMING COMPLETE. CC |
| 1/6/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 12/18/20 APPLICANT UPLOADED PLANS & PAID FEES. CP |
| 12/18/20 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |