| Miscellaneous Information / Notes |
| INTERIOR REMODEL |
| |
| |
| 11/8/21 CC EMAILED TO ALLISON AT |
| [email protected]. SCANNING FOR FILENET. |
| ATTACHMENT IN C+. FILED UNDER "K". KP |
| 11/8/21 REQUESTED CO INSTEAD OG TCO. TWO |
| INSPECTIONS NEEDED PRIOR TO ISSUANCE. TCO FEE TO |
| BE REFUNDED UNLESS THEY REQUEST IT PRIOR TO |
| PASSING TWO INSPECTIONS. T&B REPORT AND (ROOF |
| WARRANTY REQUESTED) DB |
| 11/3/21 TCO FEE ADDED KP |
| 10/29/21 TCO APPLICATION RECEIVED. WAITING FOR |
| INSPECTIONS ON MEP'S TO SAY OK FOR TCO. KP |
| 10/28/21 507 ZONING INSPECTION NOT REQUIRED PER |
| ALANA AWB |
| 3/20/21 PERMIT ISSUED. LEM |
| 3/19/21 REVIEWS COMPLETE, WAITING ON UPDATED |
| CONTRACTOR INFO TO ISSUE PERMIT. LEM |
| 3/19/2021 - PLAN REVIEW COMPLETED. PERMIT |
| LIBRARIANS NOTIFIED. TKL. |
| 3/18/2021 BUILDING & SIGNATURE REVIEWS APPROVED.PV |
| 3/16/21 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
| 3/11/21 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 3/9/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 3/3/21 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
| 2/26/21 RESUBMIT RECEIVED, INCOMING COMPLETE. CC |
| 2/23/21 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. CP |
| 2/3/2021 ASBESTOS REVIEW FAILED.PV |
| 2/3/2021 BUILDING REVIEW APPROVED.PV |
| 02/02/21 RESUBMIT RECEIVED, INCOMING COMPLETE. CC |
| 1/15/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 12/18/20 PASSED BY FIRE WITH PROVISO COMMENTS IN |
| DIGITAL PLAN REVIEW.PML |
| 12/17/20 PLANS UPLOADED, INCOMING COMPLETE. CC |
| 11/24/20 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |