| Miscellaneous Information / Notes |
| FOUNDATION PERMIT FOR FLAGLER FORTE RESIDENCES |
| |
| |
| |
| |
| |
| 4/15/22 PLANS RELEASED, PERMIT CARD UPLOADED AO |
| 4/14/22 REVIEWS COMPLETE, WAITING ON ASSIGNED |
| CONTRACTOR TO ISSUE PERMIT. LEM |
| 4/14/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT FOR IMPACT. LEM |
| 3/22/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
| COMPLETE AO |
| 2/18/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 2/04/22 APPLICANT RESUBMITTED DIGITALLY,SOME PLANS |
| VERSIONED,INCOMING COMPLETE AO |
| 1/20/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 11/10/21 PASSED BY FIRE.PML |
| 11/09/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 10/15/21 PLAN REVIEW COMPLETE, APPLICANT INVITED |
| TO RESUBMIT. CC |
| 9/9/21 PASSED BY FIRE.PML |
| 9/8/21 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 8/11/21 REVIEWS COMPLETE, APPLICNAT NEEDS TO |
| RESUBMIT. LEM |
| 6/10/21 PASSED BY FIRE.PML |
| 6/09/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 7/20/20 RESUBMIT REMINDER SENT. LEM |
| 6/19/20 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 5/27/20 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
| PLAN REVIEW.PML |
| 5/22/20 FEES PAID, INCOMING COMPLETE. LEM |
| 04/03/2020 RECEIVED ORGINAL APPLICATION LF |
| 3/25/20 PLANS UPLOADED, WAITING ON FEES. LEM |
| 3/19/20 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |