| Miscellaneous Information / Notes |
| INSTALL 100 AMP SERVICE TO SMALL CELL POLE |
| |
| |
| **CHANGED TO DIGITAL** |
| |
| |
| 12/20/22 VERIFIED PLANS IN PROJECTDOX. PLANS WILL |
| NOW BE DISCARDED PER E.SCHNEIDER REQUEST. JW |
| 1/4/2022 RENEW UNTIL 7/4/2022 SHOLDER |
| 09/24/2021 CHANGE OF CONTRACTOR $100 SPALMER |
| 7/2/21 PERMIT ISSUED. LEM |
| 5/29/21 REVIEWS COMPLETE, WAITING ON UPDATED |
| CONTRACTOR INFO TO ISSUE PERMIT. LEM |
| 5/11/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 5/6/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 03/29/21 RESUBMIT RECEIVED, INCOMING COMPLETE. CC |
| 9/22/20 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 06/17/2020 NEW INCOMING STOP WAS ADDED BECAUSE A |
| COMMUNICATIONS PERMIT MAY BE REQUIRED (CITY |
| ORDINANCE NO. 4774-18). THEREFORE, ZONING AND |
| ENGINEERING REVIEWS WERE ADDED. UPLOADED TO |
| PROJECTDOX. APPLICATION AND PLANS SENT TO LIBRARY |
| UNDER "DONE" STACK. JG. |
| 03/23/2020 ** DENIED** |
| PLAN REVIEW COMPLETE, CUSTOMER INFORMED THEY NEED |
| TO RESUBMIT. FILED IN SMALL DENIED "C". CC |
| |