| Miscellaneous Information / Notes |
| 180-INSTALL 413FT OF 1-4" HDPE CONDUIT WITH FIBER |
| ALONG ALLEY E OF N CONGRESS AVE N OF OKEECHBOOE |
| BLVD. #OE844369N |
| |
| CONTRACTOR: AT&T, FARHAN QAZI, 561-540-9275 |
| SUB: IVY SMITH, CALVIN BRADDY, 305-360-0341 |
| START DATE: 11-06-2019 |
| DURATION: 180 DAYS |
| END DATE: 05-04-2020 |
| DO NOT PARK ON THE SIDEWALK. BAGGING OF PARKING |
| METERS IS REQUIRED WHEN BLOCKING PARKING STALLS. |
| R/W & S/W RESTORATION PER CURRENT CITY STD. COPY |
| OF BORE LOGS & AS-BUILTS REQUIRED. LIGHTED |
| BARRICADES REQUIRED IF EQUIPMENT LEFT IN ROADWAY |
| OR PARKING STALL AFTER DARK OR OVER NIGHT. CONTACT |
| JANICE TARBILL 561-494-1079 FOR ALL CITY LOCATES. |
| ALL TYPE I BARRICADES TO HAVE BALLASTS OVER BOTTOM |
| RAILS. NO WORK ALLOWED BETWEEN |
| 7:00AM-9:00AM&4:00PM-6:00PM. ALL FOLLOWING |
| INSPECTIONS MUST BE CALLED IN (LISTED ON THE BACK |
| OF THE PERMIT): B800,801,802,803,804,805 |
| PLEASE BE SURE TO FOLLOW THESE SPECIAL CONDITIONS |
| (LISTED ON THE BACK OF THE PERMIT): |
| A,B,C,D,E,F,G,H,I,J,K,L,M600,601,602,603 |