| Miscellaneous Information / Notes |
| EXTENSION-01 / UTILITY IMPROVEMNETS & PAVERS |
| 180-ALLEY RESTORATION AND PAVERS 300 BLOCK |
| CLEMATIS ST SOUTH BETWEEM DIXIE & OLIVE AVE. |
| |
| CONTRACTOR: BURKJARDT CONSTRUCTION, ADAM ROSSMELL, |
| 561-659-1400 |
| START DATE: 03-15-2020 |
| DURATION: 60 DAYS |
| END DATE: 05-14-2020 |
| DO NOT PARK ON THE SIDEWALK. |
| BAGGING OF PARKING METERS IS REQUIRED WHEN |
| BLOCKING PARKING STALLS. R/W & S/W RESTORATION PER |
| CURRENT CITY STD. COPY OF BORE LOGS & AS-BUILTS |
| REQUIRED. LIGHTED BARRICADES REQUIRED IF EQUIPMENT |
| OR DUMPSTER (POD) IS LEFT IN ROADWAY OR PARKING |
| STALL AFTER DARK OR OVER NIGHT. CONTACT JANICE |
| TARBILL 561-494-1079 FOR ALL CITY LOCATES. ALL |
| TYPE I BARRICADES TO HAVE BALLASTS OVER BOTTOM |
| RAILS. NO WORK ALLOWED BETWEEN |
| 7:00AM-9:00AM&4:00PM-6:00PM. ALL FOLLOWING |
| INSPECTIONS MUST BE CALLED IN (LISTED ON THE BACK |
| OF THE PERMIT): B800,801,802,803,804,805 |
| PLEASE BE SURE TO FOLLOW THESE SPECIAL CONDITIONS |
| (LISTED ON THE BACK OF THE PERMIT): |
| A,B,C,D,E,F,G,H,I,J,K,L,M600,SEE ATTACHED |