| Miscellaneous Information / Notes |
| CONSTRUCT NEW DUMPSTER ENCLOSURE FOR RACETRAC |
| #1367 |
| |
| **ANNEXATION IN PROGRESS - ADDRESS WILL BE 2970 N |
| MILITARY TRL** |
| |
| |
| |
| |
| 05/14/2020 CHANGE OF CONTRACTOR $100 SPALMER |
| 3/12/20 GARY PICKED UP PERMIT SL |
| 12/8/19 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, PAY FEES & PICK UP PERMIT CARD. CP |
| 11/19/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 11/15/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 11/7/19 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 11/05/2019 ORIGINAL APP ROUTED TO LEM JS |
| 10/31/19 RECEIVED ORIGINAL APPLICATION. LEM |
| 10/31/2019 APRIL SUBMITTED ORIGINAL APP JS |
| 10/21/19 RESUBMIT REMINDER SENT. LEM |
| 9/20/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 9/11/19 REQUEST FOR EXPEDITE. |
| 9/11/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 8/26/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 8/7/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 6/19/19 RESUBMIT REMINDER SENT. LEM |
| 5/6/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 2/19/19 PLANS UPLOADED, INCOMING COMPLETE. LEM |
| 2/8/19 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |