| Miscellaneous Information / Notes |
| INTERIOR BUILDOUT ON 17TH AND 18TH FLOORS FOR |
| INTECH INVESTMENT |
| |
| |
| 11/10/20 CC EMAILED TO |
| [email protected]. SCANNING FOR FILENET. |
| ATTACHMENT IN C+. FILED UNDER "H". KP |
| 9/15/2020 TCO EXTENDED SEE ATTACHED REG |
| 9/14/20 TCO EXTENSION RECEIVED, ADDED FEE SH |
| 6/12/20 EMAILED TCO TO DOUG GORDON. RB |
| 6/12/20 TCO REQUEST PENDING BLDG AND FINAL MECH |
| FINAL. DB |
| 9/18/19 PLANS IN FILENET. LEM |
| 9/16/19 YOLANDA P/U PERMIT CARD SPALMER |
| 9/12/19 REVIEWSC OMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, NEEDS TO SUBMIT ORIGINAL |
| APPLICATION, NEEDS TO PICK UP PERMIT CARD. LEM |
| 9/5/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 8/30/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 8/16/19 EMAILED LETTER TO HEDRICK BROTHERS IN |
| RESPONSE TO THEIR REQUEST. WORK IS AUTHORIZED TO |
| START UP TO FIRST INSPECTION PRIOR TO PERMIT |
| ISSUANCE. RB |
| 8/6/19 PASSED BY FIRE WITH PROVISO COMMENTS IN |
| DIGITAL PLAN REVIEW.PML |
| 7/30/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 7/30/19 RECEIVED CHANGE OF CONTRACTOR, PROCESSED. |
| LEM |
| 7/29/2019 DOUG DROPPED OFF LETTER FOR R.BROWN TO |
| CONSIDER EALRY START; NEED CHANGE OF CONTRACTOR; |
| ROUTED LETTER TO R.BROWN DIRECTLY SCANNED AND |
| ATTACHED LETTER RES |
| 4/12/19 RESUBMIT REMINDER SENT. LEM |
| 3/25/19 EMAILED LETTER AUTHORIZING WORK UP TO |
| FIRST INSPECTION PRIOR TO PERMIT ISSUANCE. |
| 3/20/19 RECEIVED LETTER REQUESTING AUTHORIZATION |
| TO START WORK BEFORE PERMIT ISSUANCE. |
| 3/13/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 2/1/19 PASSED BY FIRE WITH PROVISO COMMENTS IN |
| DIGITAL PLAN REVIEW.PML |
| 1/29/19 FEES PAID, INCOMING COMPLETE. LEM |
| 1/28/19 PLANS UPLOADED, WAITING ON FEES. LEM |
| 1/28/19 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |