| Miscellaneous Information / Notes |
| CONSTRUCTION OF 18 STORY OFFICE BUILDING - |
| INCLUDING FOUNDATION, STRUCTURE, AND EXTERIOR |
| IMPROVEMENTS |
| |
| |
| 12/8/21 CO ISSUED AND EMAILED TO |
| [email protected], [email protected], |
| MIZZO@RELATEDCOM. SCANNNING FOR FILENET. |
| ATTACHMENT IN C+. FILED UNDER "M". KP |
| 9/08/2021 EXTENDED TCO ISSUED SEE ATTACHED REG |
| 8/26/21 REQUEST TO EXTEND TCO TO 12/9/21 FEE NOT |
| APPLIED YET PER CONTRACTOR ATTACHED REG |
| 6/09/21 TCC ISSUED FOR SHELL BUILDING ONLY, SEE |
| ATTACHED REG |
| 6/4/21 ZONING & LANDSCAPE OK FOR TCO AWB |
| 6/3/21 INCOMPLETE PUNCH LIST AWB |
| 5/24/2021 RECEIVED REQUEST FOR TCO OF SHELL |
| BUILDING REG (TIME STARTS FROM (5/14/21) |
| 5/14/2021 STOCKING FOR BACK OF HOUSE 1ST FL AND |
| PARTIAL 14TH FLR ONLY REG |
| 5/13/21 STOCKING FEE PAID REG |
| 4/21/21 STOCKING/TCO REQUEST RECEIVED, FEE NOT |
| APPLIED PER CONTRACTOR REQUEST REG |
| 9/11/19 PLANS IN FILENET. LEM |
| 8/26/19 WILLIAM P/U PERMIT CARD SPALMER |
| 8/22/19 REVIEWS COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, NEEDS TO SUBMIT ORIGINAL |
| APPLICATION, NEEDS TO PAY FEES, NEEDS TO PICK UP |
| PERMIT CARD. LEM |
| 8/20/19 REVIEWS COMPLETE, WAITING ON IMPACT FEES. |
| LEM |
| 8/20/19 PASSEB BY ZONING WITH PROVISOS. |
| 7/17/19 RESUBMIT REMINDER SENT. LEM |
| 6/17/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 5/1/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 4/23/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 3/26/19 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
| 3/15/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 3/6/19 RECEIVED ORIGINAL WIND TUNNEL TEST REPORTS, |
| ROUTED TO DB DESK SH |
| 2/27/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 2/20/19 PASSED BY FIRE WITH PROVISO COMMENTS IN |
| DIGITAL PLAN REVIEW.PML |
| 1/23/19 PLANS SENT, INCOMING COMPLETE. LEM |
| 1/22/19 WAITING ON CORRECTED PAGES FROM APPLICANT. |
| LEM |
| 1/14/19 RESUBMIT REMINDER SENT. LEM |
| 12/13/18 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 10/18/18 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
| PLAN REVIEW.PML |
| 9/25/18 FEES PAID, INCOMING COMPLETE. LEM |
| 9/18/18 APPLICANT UPLOADED PLANS, WAITING ON FEES. |
| CP |
| 9/12/18 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |