| Miscellaneous Information / Notes |
| STRUCTURE FOR FOUR STORY MEDICAL BUILDING |
| (FOUNDATION PERMIT EXPANED BY REVISION 19010624) |
| |
| |
| |
| |
| 4/5/19 TERRY DROPPEDO OFF PAPERWORK INSPECTION |
| REPORTS GAVE TO D.HARVEY CUSTOMER DID NOT KNOW WHO |
| IT WAS FOR? RES |
| 2/4/19 - OLD DESCRIPTION (FOUNDATION ONLY): |
| STRUCTURAL FOUNDATION WORK (ALL STRUCTURAL |
| COMPONENTS UP TO 0'0" AFF ELEVATION) |
| 2/4/19 MATT PICKED UP PERMIT CARD SL |
| 1/31/19 APPLICANT NEEDS TO PICK UP NEW PERMIT CARD |
| AT NO CHARGE. LEM |
| 1/22/19 FEES FOR STRUCTURE VALUE ADDED AND PAID IN |
| FULL; REVIEW IS UNDER REVISION 19010624 SH |
| 1/19/19 FOUNDATION PERMIT EXPANED BY STRUCTURE |
| REVISION 19010624, PERMIT TYPE WILL BE CHANGED AT |
| TIME OF STRUCTURE REVISION ISSUANCE. VALUE HAS |
| BEEN INCREASED BY $3,744,244 FOR A TOTAL STRUCTURE |
| VALUE OF $3,994,244 ($250,000 FOUNDATION + |
| $3,744,244 STRUCTURE) SH |
| |
| (OLD DESCRIPTION: STRUCTURAL FOUNDATION WORK (ALL |
| STRUCTURAL COMPONENTS UP TO 0'0" AFF ELEVATION) |
| |
| |
| |
| |
| |
| 12/27/18 PLANS IN FILENET. LEM |
| 10/3/18 PLANS RELEASED. LEM |
| 10/2/18 ECS FLORIDA-MIGUEL SANTIGO IS SI FOR THE |
| PROJECT SEE ATTACHMENTS REG |
| 10/2/18 GAVE PERMIT CARD TO DAVE SH |
| 10/2/18 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 9/30/18 PLAN REVIEW COMPLETE APPLICANT NEEDS TO |
| RESUBMIT. CP |
| 9/28/18 !!!!PLUMBING APPROVED WITH PROVISO SHALL |
| COMPLY BEFORE PLUMBING PERMIT CAN BE ISSUED./GPJ |
| !!! |
| 9/27/18 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
| 9/25/18 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 9/25/18 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 9/24/18 DENIED SENT TO LIB BY GPJ |
| 8/23/18 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
| PLAN REVIEW.PML |
| 8/17/18 FEES PAID, INCOMING COMPLETE. LEM |
| 8/14/18 PLANS UPLOADED, WAITING ON FEES. LEM |
| 8/14/18 APPLICANT INVITED TO UPLOAD PLANS & PAY |
| FEES. CP |