| Miscellaneous Information / Notes |
| MASTER #17120610 - INTERIOR IMPROVEMENTS FOR |
| ENTIRE SPACE, PHASED PERMITTING (B, A2, S1),4 FL |
| |
| |
| |
| |
| |
| 7/11/19 MICHAEL P/U CO SPALMER |
| 6/25/2019 1ST TCO EXTENSION TO 9/25/2019 ORIGINAL |
| IN CO BOX UNDER Q REG |
| 5/24/19 MICHAEL P/U TCO SPALMER |
| 3/29/19 SENT EMAIL TO JONI MORGAN TO P/U UPDATED |
| TCO. IN CO BOX UNDER "Q". RB |
| 3/28/19 SENT EMAIL TO JONI MORGAN TO P/U TCO. IN |
| CO BOX UNDER "Q". RB |
| 3/26/19 STOCKING CERTIFICATE ISSUED AND SENT BY |
| EMAIL TO JONI MORGAN. RB |
| 3/12/18 RECEIVED STOCKING/TCO REQUEST. ATTACHED |
| SAK |
| |
| |
| ***OK TO RELEASE PRINT HOLD TO PRINT PERMIT, EMAIL |
| [email protected], [email protected] WHEN ISSUED** SH |
| |
| |
| |
| **PER SKENNEDY, PLAN REVIEW TO BE DONE UNDER FBC |
| 2014 AS IT IS A CONTINUANCE OF THE STRUCTURE |
| PERMIT DONE UNDER THE SAME CODE** |
| |
| 12/28/18 PLANS IN FILENET. LEM |
| 11/2/18 REVIEWS COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, NEEDS TO PAY REMAINING FEES, NEEDS |
| TO PICK UP PERMIT CARD. LEM |
| 10/31/18 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 10/24/18 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 9/25/18 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 9/22/18 RESUBMIT REMINDER SENT. CP |
| 8/23/18 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 7/18/18 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 6/18/18 CHANGE OF CONTRACTOR TO QUEST CONTRACTING |
| LLC. SLEE |
| 6/11/18 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 4/17/18 APPLICANT PAID FEES, INCOMING COMPLETE. CP |
| 4/11/18 PLANS UPLOADED, WAITING ON FEES. LEM |
| 4/3/18 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |