| Miscellaneous Information / Notes |
| DEMOLISH STRUCTURE |
| |
| |
| |
| |
| 4/27/18 MORIAH P/U PERMIT SPALMER |
| 4/24/18 NICKY DID CHANGE OF CONTRACTOR FOR NEW |
| PERMIT CARD, PERMIT APPROVED BY DOUG SL |
| 3/27/18 PERMIT PUT IN HOLD STATUS. ELKIS |
| CONSTRUCTION WAS CITED BY DBPR INVESTIGATOR FOR |
| OBTAINING THE PERMIT ON BEHALF OF AN UNLICENSED |
| COMPANY. THE DBPR HAS DETERMINED THAT ELKIS DOES |
| NOT HAVE A VALID CONTRACT WITH THE PROPERTY OWNER. |
| RB |
| 2/21/18 FELIX P/U PERMIT SPALMER |
| 2/21/18 ISSUED, EMAILED APPLICANT, CARD FILED AT |
| FRONT COUNTER 'E' SH |
| 2/13/18 ELIEZER P/U PERMIT SPALMER |
| 1/22/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED, |
| READY TO BE PICKED UP, FILED UNDER SMALL "E". CP |
| 1/19/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
| "E". CP |
| 1-6-18 DID GROUP REVIEW OF 3 APPLICATIONS AND MADE |
| ONE PHONE CALL TO CONTR. LEFT MESSAGE TO CALL ME |
| MONDAY MORNING ON OUTSTANDING ITEMS TO ISSUE DEMO |
| PERMIT. TM |
| 1/4/18 RESUB ADDRESSING DENIED COMMENTS NATALEE |
| 12/27/17 CONTRACTOR ADDED SL |
| 12/7/17 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
| "TBD". CP |
| 12-4-17 MOVED TO ENGINEERING'S MAILBOX. E-MAILED |
| CONTRACTOR. TM |
| 11/20/17 ROUTED TO TMOORE'S DESK. LEM |
| 11/16/2017 AWAITING ADD'L DOCUMENTS BEFORE PLANS |
| CAN BE REVIEWED JS |