| Miscellaneous Information / Notes |
| 2 STORY DETACHED ACCESSORY LIVING SPACE |
| |
| |
| ***** TRAVELING WITH 17100908 ***** |
| |
| 12/27/17 DAVID PICKED UP PERMIT RES |
| 12/27/17 E-MAILED CONTRACTOR. PERMIT PACKAGE |
| UPFRONT IN LARGE PLANS SHELF UNDER "A". JG. |
| 12/27/17 PLUMB APPROVED SENT TO JG BY GPJ |
| 12/21/17 DAVID BOWDEN SUBMITTED REVISED PLUMBING |
| RISER DIAGRAM. PLANS ON JULIO'S DESK. JG. |
| 12/13/17 DAVID BOWDEN SUBMITTED REVISED ENERGY |
| CALCULATIONS AND EQUIPMENT SIZING CALCULATIONS. |
| PLANS ON JULIO'S DESK. JG. |
| 11/22/17 MET WITH ARCHITECT ANTHONY HARRINGTON AND |
| CONFIRMED WITH FMITTNER THAT REAR BUILDING CANNOT |
| CONSTITUTE A SEPARATE DWELLING UNIT. ONLY ONE |
| ELECTRICAL SERVICE ID ALLOWED.CHANGED PERMIT |
| DESCRIPTION AND ADDED US C-404 CODE TYPE TO |
| INDICATE ADDITION. ASSURED PERMIT TYPE IS |
| ADDITION. SAK |
| 11/16/17 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
| "A". CP |
| 11/15/17 PLUMB DENIED SENT TO LIB/GPJ |
| 10/23/2017 SCOTT RESUB TO ADDRESS DENIED COMMENTS |
| JS |
| 09/26/2017 DAVID SIGNED OUT PLANS JS |
| 9/26/17 IN LARGE DENIED A CONT CUST/GPJ |