| Miscellaneous Information / Notes |
| INTERIOR BUILDOUT OF NEW DENTAL IMPLANT FACILITY |
| |
| |
| |
| |
| |
| |
| 12/20/2018 CERTIFICATE OF COMPLETION PRINTED AND |
| PLACED AT FRONT COUNTER, FILED UNDER H WITH COPY |
| SENT TO SCANNING. COPY OF CERTIFICATE ALSO |
| ATTACHED TO THIS PERMIT. MM |
| 4/10/18 KEVIN P/U TCO SPALMER |
| 4/10/18 TCO PRINTED, FEES ADDED. IN CO BOX UNDER H |
| DH |
| 4/5/18 STILL NO FINAL INSPECTION REQUESTS FOR |
| STOCKING IN THE SYSTEM. CALLED LAUREN AND ADVISED. |
| SHE STATED THE SUPERINTENDENT WAS PLANNING TO CALL |
| FOR INSPECTIONS AND SHE WOULD FOLLOW UP WITH HIM. |
| DH |
| 3/27/18 REQUEST FOR TCO ROUTED TO DOUG HARVEY |
| SPALEMR |
| 2/9/18 LAUREN P/U PERMIT SPALMER |
| 2/9/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED, |
| READY TO BE PICKED UP, FILED UNDER LARGE "TBD". CP |
| 1/24/18 PASSED BY FIRE WITH PROVISO COMMENTS, |
| RETURNED TO C25.PML |
| 1/23/18 PLUMB APPROVED RETURN TO C25/GPJ |
| 1/18/18 LAUREN RESUB TO ADDRESS DENIED COMMENTS |
| SHOLDER |
| 1/5/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
| "TBD3". CP |
| 1/5/18 DENIED SENT TO LIB BY GPJ |
| 12/1/17 ASHLEY RESUB TO ADDRESS DENIED COMMENTS |
| 11/8/17 PLANS IN LARGE DENIED TBD3 / CC |
| 10/18/17 TABITHA P/U 1 SET OF PLANS NATALEE |
| 10/18/17 - DENIED/CONTACTED CONTR./PLACED IN LARGE |
| DENIED UNDER "TBD-3.TKL. |
| 9/14/17 MECH FAILED/RETURNED TO C17/CC |